Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 549
Message text: Activity dates exist for WBS element &. You cannot delete
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CJ549
- Activity dates exist for WBS element &. You cannot delete ?The SAP error message CJ549 indicates that you are trying to delete a Work Breakdown Structure (WBS) element that has existing activity dates associated with it. This is a common issue in project management within SAP, particularly when dealing with project structures and their associated activities.
Cause:
The error occurs because:
- Activity Dates Exist: The WBS element has one or more activities that have been scheduled or have actual dates assigned to them. SAP does not allow the deletion of a WBS element if it is linked to any activities that have been planned or executed.
- Dependencies: The WBS element may have dependencies or relationships with other project elements, making it necessary to maintain its integrity in the project structure.
Solution:
To resolve this error, you can take the following steps:
Check Activity Assignments:
- Navigate to the WBS element in question and check if there are any activities assigned to it. You can do this using transaction codes like CJ20N (Project Builder) or CJ03 (Display WBS Element).
Delete or Change Activity Dates:
- If you find activities associated with the WBS element, you will need to either delete those activities or change their dates to remove the dependency. This can be done in the Project Builder (CJ20N) or through the respective activity management transactions.
Use the Correct Deletion Method:
- If you are sure that the WBS element should be deleted, ensure that all associated activities are either deleted or their dates are reset. After that, you can attempt to delete the WBS element again.
Check for Other Dependencies:
- Ensure that there are no other dependencies or links to other project elements that might prevent deletion. This includes checking for any assigned resources, costs, or other project management elements.
Consult Documentation or Support:
- If you are unsure about the implications of deleting a WBS element or if you encounter further issues, consult your organization's SAP documentation or reach out to your SAP support team for assistance.
Related Information:
By following these steps, you should be able to resolve the CJ549 error and successfully manage your WBS elements in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ548
Select a network first
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ547
Finish date is in the past
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ550
Define network profile first
What causes this issue? You have not entered a network profile in the project profile. Therefore, you cannot detail dates.System Response INCLUDE ...
CJ551
Enter dates in the project definition first
What causes this issue? You have not entered any start or finish dates in the project definition. Therefore you do not have a time frame to work with...