Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 533
Message text: Either select only one WBS element or no WBS element
The finish date that you entered for the activity is later than the
finish date in the superior WBS element.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
If you use top-down planning, the activity dates should lie within the
time frame of the superior WBS element.
The system checks the dates when you save. If there is a scheduling
conflict, you must adjust the dates accordingly.
Error message extract from SAP system. Copyright SAP SE.
CJ533
- Either select only one WBS element or no WBS element ?The SAP error message CJ533 ("Either select only one WBS element or no WBS element") typically occurs in the context of project management within SAP, particularly when dealing with Work Breakdown Structure (WBS) elements in transactions related to project planning, budgeting, or reporting.
Cause:
This error arises when a user attempts to perform an action that requires either a single WBS element or no WBS element at all, but multiple WBS elements are selected instead. This can happen in various scenarios, such as:
To resolve this error, you can follow these steps:
Check Your Selection: Ensure that you have selected only one WBS element if the transaction requires it. If you do not need to specify a WBS element, make sure none are selected.
Modify Your Input: If you are using a selection screen or input fields, adjust your input to comply with the requirement of the transaction. For example, if you are in a report or planning transaction, deselect any additional WBS elements.
Review Transaction Requirements: Consult the documentation or help text for the specific transaction you are using to understand its requirements regarding WBS elements.
Use Filters: If you are working with a list of WBS elements, consider using filters to narrow down your selection to a single element.
Consult with Colleagues or Support: If you are unsure about the correct WBS element to select or the purpose of the transaction, consult with colleagues or your SAP support team for guidance.
By following these steps, you should be able to resolve the CJ533 error and proceed with your project management tasks in SAP.
Get instant SAP help. Start your 7-day free trial now.
CJ532
Schedule conflicts exist. See log
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ531
No dates in WBS element &. Reconciliation not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ534
No WBS elements exist
What causes this issue? There are no WBS elements defined for the project. You cannot carry out time scheduling.System Response INCLUDE 'NA_AL...
CJ535
Missing data for time scheduling in project profile &
What causes this issue? In project definition &V1&, you have not maintained all of the data necessary for maintaining dates in the work break...
Click on this link to search all SAP messages.