Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 535
Message text: Missing data for time scheduling in project profile &
In project definition &V1&, you have not maintained all of the data
necessary for maintaining dates in the work breakdown structure.
The minimum requirement for planning dates is the maintenance of the
following in the project definition:
Planning method for the basic dates
Planning method for the forecast dates
Time unit
Network profile
Assignments to network
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
Fill in the missing data in project definition &V1&.
You can also change the network profile from time scheduling.
Error message extract from SAP system. Copyright SAP SE.
CJ535
- Missing data for time scheduling in project profile & ?The SAP error message CJ535, which indicates "Missing data for time scheduling in project profile," typically arises when there are issues related to the configuration of the project profile or the project itself. This error is often encountered in the context of project management within SAP, particularly when dealing with project planning and scheduling. Causes of Error CJ535 Incomplete Project Profile Configuration: The project profile may not have been fully configured with the necessary settings for time scheduling. This includes missing parameters related to scheduling methods, planning types, or other relevant settings. Missing Time-Related Data: The project may lack essential time-related data, such as start and finish dates, or the necessary planning elements that are required for scheduling. Incorrect Assignment of Project Profile: The project profile assigned to the project may not be appropriate for the type of project being created or managed. Missing Dependencies: There may be missing dependencies or relationships between tasks that
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ534
No WBS elements exist
What causes this issue? There are no WBS elements defined for the project. You cannot carry out time scheduling.System Response INCLUDE 'NA_AL...
CJ533
Either select only one WBS element or no WBS element
What causes this issue? The finish date that you entered for the activity is later than the finish date in the superior WBS element.System Response ...
CJ536
No new networks exist
What causes this issue? There are no newly created networks in the system for you to delete.System Response INCLUDE 'NA_ALLG_NOFUNKTION' O...
CJ537
Schedule conflicts found for basic dates. Please correct
INCLUDE CJ573 OBJECT DOKU ID NAError message extract from SAP system. Copyright SAP SE. ...