Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 532
Message text: Schedule conflicts exist. See log
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CJ532
- Schedule conflicts exist. See log ?The SAP error message CJ532, which states "Schedule conflicts exist. See log," typically occurs in the context of project management within SAP, particularly when dealing with project planning and scheduling in the Project System (PS) module. This error indicates that there are conflicts in the scheduling of activities or tasks within a project.
Causes of CJ532 Error
- Overlapping Activities: Two or more activities may be scheduled to occur at the same time, which can lead to resource conflicts.
- Resource Availability: Resources assigned to tasks may not be available during the scheduled time, leading to conflicts.
- Incorrect Dependencies: The relationships between tasks (e.g., finish-to-start, start-to-start) may not be set up correctly, causing scheduling issues.
- Duration Issues: The duration of tasks may be set incorrectly, leading to overlaps.
- Calendar Settings: The project or resource calendars may not align, causing scheduling conflicts.
- Capacity Constraints: If the project has capacity constraints that are not met, it can lead to scheduling conflicts.
Solutions to CJ532 Error
- Check the Log: The first step is to check the detailed log associated with the error message. This log will provide specific information about which activities are conflicting.
- Review Activity Scheduling: Go through the scheduled activities and check for overlaps. Adjust the start and finish dates as necessary.
- Adjust Resource Assignments: Ensure that resources are not over-allocated. You may need to reassign resources or adjust their availability.
- Verify Dependencies: Check the dependencies between tasks to ensure they are set up correctly. Adjust them if necessary.
- Modify Task Durations: Review the durations of tasks to ensure they are realistic and do not lead to overlaps.
- Check Calendar Settings: Ensure that the project and resource calendars are correctly set up and aligned.
- Capacity Planning: If capacity constraints are causing the issue, consider adjusting the project plan to accommodate available resources.
Related Information
By following these steps and utilizing the available tools, you should be able to resolve the CJ532 error and ensure that your project scheduling is accurate and conflict-free.
Get instant SAP help. Start your 7-day free trial now.
CJ531
No dates in WBS element &. Reconciliation not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ530
Schedule conflicts found. Correct dates
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ533
Either select only one WBS element or no WBS element
What causes this issue? The finish date that you entered for the activity is later than the finish date in the superior WBS element.System Response ...
CJ534
No WBS elements exist
What causes this issue? There are no WBS elements defined for the project. You cannot carry out time scheduling.System Response INCLUDE 'NA_AL...