Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 505
Message text: WBS element & is locked for time scheduling
WBS element &V1& has the status "locked dates." You cannot maintain any
dates.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
You can unlock the dates in the work breakdown structure.
Error message extract from SAP system. Copyright SAP SE.
CJ505
- WBS element & is locked for time scheduling ?The SAP error message CJ505 indicates that a Work Breakdown Structure (WBS) element is locked for time scheduling. This typically occurs when there are certain conditions that prevent the scheduling of time-related activities on that WBS element. Here’s a breakdown of the cause, potential solutions, and related information:
Cause:
- Locked by Another User: The WBS element may be locked by another user who is currently processing or updating it.
- Status of WBS Element: The WBS element might be in a status that does not allow time scheduling (e.g., it could be set to "Completed" or "Closed").
- Project Structure: The project structure may have been changed, or the WBS element may not be properly assigned to a project.
- Authorization Issues: The user may not have the necessary authorizations to schedule time on the WBS element.
- System Settings: Certain system settings or configurations may prevent scheduling on specific WBS elements.
Solution:
- Check Locks: Use transaction code SM12 to check if the WBS element is locked by another user. If it is, you may need to wait for that user to release the lock or contact them to resolve the issue.
- Review WBS Status: Check the status of the WBS element using transaction CJ03 (Display WBS) to ensure it is not in a status that prevents scheduling. If it is, you may need to change its status.
- Project Assignment: Ensure that the WBS element is correctly assigned to a project and that the project is active.
- Authorization Check: Verify that you have the necessary authorizations to perform time scheduling on the WBS element. You may need to contact your SAP security team for assistance.
- Consult Configuration: If the issue persists, consult with your SAP Basis or configuration team to review any system settings that may be affecting the scheduling capabilities.
Related Information:
If the problem continues after trying the above solutions, it may be beneficial to escalate the issue to your SAP support team for further investigation.
Get instant SAP help. Start your 7-day free trial now.
CJ504
WBS element & is not an account assignment element
What causes this issue? The activity or the activities that you want to assign to a WBS element are in a network which has account assignments at the...
CJ503
Dates in WBS element & not current
What causes this issue? WBS element &V1& is assigned to activities in a network. This network has since been rescheduled. In certain cases th...
CJ506
Finish date for WBS element & no longer fits
What causes this issue? The finish date which you entered for WBS element &V1& does not lie within the time frame of the superior WBS element...
CJ507
Start date for WBS element & no longer fits
What causes this issue? The start date which you entered for WBS element &V1& does not lie within the time frame of the superior WBS element ...
Click on this link to search all SAP messages.