Do you have any question about this error?
Message type: E = Error
Message class: CJ - Project master data and structure
Message number: 506
Message text: Finish date for WBS element & no longer fits
The finish date which you entered for WBS element &V1& does not lie
within the time frame of the superior WBS element any more.
There will be scheduling conflicts if you continue time scheduling.
INCLUDE 'NA_ALLG_VERARBEITUNG' OBJECT DOKU ID TX
You can check and reconcile dates using the menu option <LS>Edit</>.
Error message extract from SAP system. Copyright SAP SE.
CJ506
- Finish date for WBS element & no longer fits ?The SAP error message CJ506 ("Finish date for WBS element & no longer fits") typically occurs in the context of project management within SAP, particularly when dealing with Work Breakdown Structure (WBS) elements. This error indicates that the finish date of a WBS element is inconsistent with the dates of its related activities or the overall project.
Cause:
- Inconsistent Dates: The finish date of the WBS element is set earlier than the finish date of one or more of its associated activities or tasks.
- Project Structure Changes: Changes made to the project structure, such as rescheduling activities or changing dependencies, can lead to this inconsistency.
- Manual Date Adjustments: If users manually adjust the dates of WBS elements or activities without considering their interdependencies, it can result in this error.
- Planning Settings: Incorrect planning settings or parameters in the project management configuration can also lead to date mismatches.
Solution:
To resolve the CJ506 error, you can take the following steps:
Check Activity Dates: Review the start and finish dates of all activities associated with the WBS element. Ensure that the finish date of the WBS element is later than or equal to the latest finish date of its activities.
Adjust WBS Dates: If necessary, adjust the finish date of the WBS element to align with the activities. This can be done in the WBS element's details in the project management module.
Re-schedule Activities: If the activities need to be rescheduled, adjust their dates accordingly to ensure they fit within the overall project timeline.
Review Dependencies: Check for any dependencies between activities and the WBS element. Ensure that all dependencies are correctly defined and that they do not conflict with the WBS dates.
Use Project Planning Tools: Utilize SAP's project planning tools to visualize the project timeline and identify any discrepancies in dates.
Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing WBS elements and resolving date-related issues.
Related Information:
By following these steps, you should be able to resolve the CJ506 error and ensure that your project planning remains consistent and accurate.
Get instant SAP help. Start your 7-day free trial now.
CJ505
WBS element & is locked for time scheduling
What causes this issue? WBS element &V1& has the status "locked dates." You cannot maintain any dates.System Response INCLUDE ...
CJ504
WBS element & is not an account assignment element
What causes this issue? The activity or the activities that you want to assign to a WBS element are in a network which has account assignments at the...
CJ507
Start date for WBS element & no longer fits
What causes this issue? The start date which you entered for WBS element &V1& does not lie within the time frame of the superior WBS element ...
CJ508
WBS element & has no activities
What causes this issue? WBS element &V1& does not have any activities and therefore also has no dates for comparison.System Response INCLUD...