Message text: Activity dates are not within WBS dates
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
CJ167
- Activity dates are not within WBS dates ?The SAP error message CJ167 ("Activity dates are not within WBS dates") typically occurs when you are trying to assign or change the dates of an activity in a project that fall outside the defined dates of the Work Breakdown Structure (WBS) element. This is a common issue in project management within SAP, particularly in the Project System (PS) module.
Cause:
- Date Mismatch: The start or finish dates of the activity you are trying to create or modify are outside the start and finish dates of the associated WBS element.
- WBS Element Configuration: The WBS element may have been configured with specific start and end dates that do not accommodate the activity's dates.
- Project Planning Changes: Changes in project planning or scheduling that have not been reflected in the WBS dates can lead to this error.
Solution:
To resolve the CJ167 error, you can take the following steps:
Check WBS Dates:
- Navigate to the WBS element in question and check its start and finish dates. Ensure that they encompass the dates of the activity you are trying to create or modify.
Adjust Activity Dates:
- If the WBS dates are correct and should remain unchanged, adjust the start and finish dates of the activity to fall within the WBS dates.
Change WBS Dates:
- If the activity dates are correct and should remain unchanged, consider adjusting the WBS element's start and finish dates to include the activity dates. This can be done in the WBS element's master data.
Review Project Structure:
- Ensure that the overall project structure and scheduling are aligned. Sometimes, a higher-level WBS element may have constraints that affect its sub-elements.
Consult Project Management Guidelines:
- If you are unsure about making changes, consult your project management guidelines or speak with a project manager to ensure that any changes align with project objectives.
Related Information:
By following these steps, you should be able to resolve the CJ167 error and ensure that your project activities are correctly aligned with the WBS dates.
Get instant SAP help. Sign up for our Free Essentials Plan.
CJ166
No network is assigned to WBS element "&"
What causes this issue? You are attempting to assign a sales document to a network using a WBS element. However, the WBS element that you have select...
CJ165
Dates from & WBS element(s) were adjusted
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
CJ168
Activities in network "&" are assigned to several WBS elements
What causes this issue? You want check the availability of a material via the WBS element. The system checks material availability using the network ...
CJ169
WBS element is displayed by number
What causes this issue? In the project profile settings WBS elements are referred to by their short ID or description. However this transaction refer...