Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 078
Message text: WBS element &: Forwards scheduling is not possible without a start date
The WBS element is not scheduled.
Enter a basic start date in at least one of the objects mentioned
above.
Network scheduling:
Enter a basic start date in at least one network header.
Error message extract from SAP system. Copyright SAP SE.
C7078
- WBS element &: Forwards scheduling is not possible without a start date ?The SAP error message C7078 indicates that a Work Breakdown Structure (WBS) element is missing a start date, which is necessary for forwards scheduling. This error typically arises in project management scenarios where scheduling is dependent on defined dates for tasks or elements.
Cause:
- Missing Start Date: The primary cause of this error is that the WBS element does not have a defined start date. Forwards scheduling requires a starting point to calculate the subsequent dates for tasks.
- Incorrect Configuration: There may be configuration issues in the project management settings that prevent the assignment of a start date.
- Data Entry Errors: During the creation or modification of the WBS element, the start date may not have been entered or saved correctly.
Solution:
Define a Start Date:
- Navigate to the WBS element in question.
- Ensure that a valid start date is entered in the relevant fields. This can typically be done in the project definition or WBS element details.
- Save the changes.
Check Project Settings:
- Review the project settings to ensure that the scheduling parameters are correctly configured.
- Ensure that the project type allows for forwards scheduling and that all necessary fields are filled out.
Review Dependencies:
- Check if there are any dependencies or constraints that might be affecting the scheduling of the WBS element.
- Ensure that all predecessor tasks have been defined and that their dates are set correctly.
Use Transaction Codes:
- You can use transaction codes like
CJ20N
(Project Builder) to access and modify the WBS element.- Alternatively, use
CJ02
(Change WBS Element) to directly edit the WBS element.Consult Documentation:
- Refer to SAP documentation or help resources for additional guidance on project scheduling and WBS management.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in project management within SAP.
Get instant SAP help. Start your 7-day free trial now.
C7077
Overall netw. sched.: No conflicts between basic and scheduled dates
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7076
Overall network scheduling: Basic start is after scheduled start
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7079
WBS element &: Backwards scheduling is not possible without a finish date
CAUSE& You want to backward schedule a WBS element, although a basic finish date has not been entered in either the projection definition, WBS el...
C7080
Program CX_TCX00 executed successfully
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...