Do you have any question about this error?
Message type: E = Error
Message class: C7 - Scheduling
Message number: 079
Message text: WBS element &: Backwards scheduling is not possible without a finish date
The WBS element is not scheduled.
Enter a basic finish date in at least one of the objects mentioned
above.
Network scheduling:
Enter a basic finish date in at least one network header.
Error message extract from SAP system. Copyright SAP SE.
C7079
- WBS element &: Backwards scheduling is not possible without a finish date ?The SAP error message C7079 indicates that backward scheduling cannot be performed for a Work Breakdown Structure (WBS) element because it lacks a finish date. This error typically arises in project management scenarios where scheduling is critical, and the system requires a defined end date to calculate the project timeline effectively.
Cause:
- Missing Finish Date: The primary cause of this error is that the WBS element does not have a defined finish date. Backward scheduling relies on knowing when a project or task is supposed to end to calculate the start dates of preceding tasks.
- Incorrect Settings: There may be settings in the project management configuration that prevent the system from determining a finish date.
- Incomplete Project Planning: The project may not be fully planned, meaning that not all necessary dates and dependencies have been established.
Solution:
Define a Finish Date:
- Navigate to the WBS element in question and ensure that a finish date is set. This can typically be done in the project planning or WBS element maintenance screens.
- If the finish date is not known, you may need to estimate it based on project requirements or milestones.
Check Project Settings:
- Review the project settings to ensure that all necessary parameters for scheduling are correctly configured. This includes checking the project type and ensuring that it allows for backward scheduling.
Review Dependencies:
- Ensure that all tasks and activities related to the WBS element have been properly defined, including their dependencies and durations. This will help the system calculate the finish date.
Use Forward Scheduling:
- If backward scheduling is not feasible, consider using forward scheduling instead, which calculates the finish date based on the start date and duration of tasks.
Consult Documentation:
- Refer to SAP documentation or help resources for specific instructions on how to set finish dates and configure project scheduling.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with an SAP expert or your organization's SAP support team for further assistance.
Get instant SAP help. Start your 7-day free trial now.
C7078
WBS element &: Forwards scheduling is not possible without a start date
CAUSE& You want to forward schedule a WBS element, although a basic start date has not been entered in either the projection definition, WBS elem...
C7077
Overall netw. sched.: No conflicts between basic and scheduled dates
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7080
Program CX_TCX00 executed successfully
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
C7081
Program CX_TCX00 executed with a warning
What causes this issue? The program CX_TCX00 has finished succesfully. There are entries in the scheduling tables with the same key fields. These ent...
Click on this link to search all SAP messages.