Do you have any question about this error?
Message type: E = Error
Message class: C2 - Other messages production orders
Message number: 364
Message text: Operation &1: Parts provided (subcontracting components) not supported
"Kit-to-stock" has been activated in the production scheduling profile
&V3& of order &V2&. It is therefore not possible to provide components
for an externally processed operation with subcontracting.
During the reading of the master data, this message appears in the log
as a warning. At the time of order release, this message is an error
message and release is terminated.
Change the production scheduling profile in the order header, unset the
subcontracting indicator, or assign the components to a different
operation.
Error message extract from SAP system. Copyright SAP SE.
C2364
- Operation &1: Parts provided (subcontracting components) not supported ?The SAP error message C2364, which states "Operation &1: Parts provided (subcontracting components) not supported," typically occurs in the context of production orders or routing when dealing with subcontracting processes. This error indicates that the system has encountered an issue with the components that are being provided for a subcontracting operation.
Cause:
- Incorrect Configuration: The routing or production order may not be properly configured to handle subcontracting components.
- Missing Component Assignment: The components required for the subcontracting operation may not be correctly assigned in the BOM (Bill of Materials) or routing.
- Operation Type: The operation type in the routing may not support subcontracting components.
- Material Master Settings: The material master settings for the components may not be set up correctly for subcontracting.
- Subcontracting Indicator: The subcontracting indicator may not be set for the relevant materials.
Solution:
- Check Routing: Review the routing for the operation in question. Ensure that the operation is set up to allow subcontracting and that the components are correctly assigned.
- Review BOM: Verify that the BOM includes the necessary components for the subcontracting operation and that they are marked as subcontracting components.
- Material Master: Check the material master records for the components to ensure that they are configured for subcontracting. Look for the "Subcontracting" indicator in the material master.
- Operation Type: Ensure that the operation type used in the routing supports subcontracting. You may need to change the operation type if it does not.
- Subcontracting Info Record: Ensure that there is a valid subcontracting info record for the materials involved. This record should specify the vendor and the components to be provided.
- Consult Documentation: Refer to SAP documentation or help resources for specific configuration settings related to subcontracting.
Related Information:
CS01
(Create BOM), CS02
(Change BOM), CA01
(Create Routing), and CA02
(Change Routing) to make necessary adjustments.If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production and subcontracting processes.
Get instant SAP help. Start your 7-day free trial now.
C2363
Operation &1: Automatic goods receipt not possible
What causes this issue? "Kit-to-stock" has been activated in the production scheduling profile &V3& of order &V2&. It is th...
C2362
Requirement dates/times of components in order &1 do not match up
What causes this issue? "Kit-to-stock" has been activated in the production scheduling profile &V2& of order &V1&. For this...
C2365
Operation &1: Non-supported trigger points assigned
What causes this issue? "Kit-to-stock" has been activated in the production scheduling profile &V3& of order &V2&. It is th...
C2366
Operation release not possible in case of kit-to-stock orders
What causes this issue? 'Kit-to-stock' has been activated in the production scheduling profile &V2& of order &V1&. It is th...
Click on this link to search all SAP messages.