Do you have any question about this error?
Message type: E = Error
Message class: BQ - Messages for Budgeting and Planning
Message number: 040
Message text: Overall release less than cumulative release
The overall release of several fund center(s)/commitment item(s) is
smaller than the accumulated release.
The accumulated release comes from the total of annual releases.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
BQ040
- Overall release less than cumulative release ?The SAP error message BQ040 ("Overall release less than cumulative release") typically occurs in the context of purchasing documents, such as purchase orders or contracts, when the overall release amount is less than the cumulative release amount. This can happen in scenarios where the system is trying to validate the release strategy for a document, and the total amount that has been released (cumulative release) exceeds the overall amount that is allowed to be released.
Cause:
- Release Strategy Configuration: The release strategy may be incorrectly configured, leading to discrepancies between the overall release and cumulative release amounts.
- Manual Changes: Manual adjustments to the purchase order or contract amounts may have been made, resulting in an inconsistency.
- Incomplete Release Process: The release process may not have been completed correctly, leading to an incorrect overall release amount.
- Document Changes: Changes to the document after it has been released can also lead to this error if the overall release is not adjusted accordingly.
Solution:
- Check Release Strategy: Review the release strategy configuration in the system to ensure that it is set up correctly. Make sure that the thresholds for overall and cumulative releases are properly defined.
- Review Document Amounts: Check the amounts in the purchase order or contract. Ensure that the overall release amount is greater than or equal to the cumulative release amount.
- Adjust Release Amounts: If necessary, adjust the overall release amount to be equal to or greater than the cumulative release amount. This may involve changing the release status or amounts in the document.
- Reprocess the Release: If the document has been released incorrectly, you may need to reprocess the release strategy. This can involve resetting the release status and re-releasing the document.
- Consult with SAP Support: If the issue persists, consider reaching out to SAP support for further assistance, especially if it appears to be a system bug or configuration issue.
Related Information:
By following these steps, you should be able to identify the cause of the BQ040 error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
BQ039
- &: & <& (&)
What causes this issue? Annual release &V2& &V4& for funds center/commitment item &V1& is smaller than the distributed releas...
BQ038
Annual release & less than distributed release
What causes this issue? The annual release for one or more funds center(s)/commitment item(s) is less than the distributed release.System Response T...
BQ041
- &: & <& (&)
What causes this issue? Overall release &V2& &V4& in funds center/commitment item &V1& is less than cumulative release &V...
BQ046
Overall budget less than overall release
What causes this issue? The overall budget for one or more funds center(s)/commitment item(s) is less than the overall funds release.System Response ...