Message text: Overall budget less than distributed budget
The total budget for one or more of the WBS elements is less than the
distributed budget.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
BQ001
- Overall budget less than distributed budget ?The SAP error message BQ001 ("Overall budget less than distributed budget") typically occurs in the context of budget management within SAP, particularly in the Public Sector Management (PSM) or Controlling (CO) modules. This error indicates that the total budget allocated for a particular cost center, internal order, or project is less than the amount that has already been distributed or committed against that budget.
Cause:
- Budget Overcommitment: The most common cause is that the total budget for a specific cost center or project has been exceeded by the sum of all commitments and actual expenditures.
- Incorrect Budget Settings: There may be an error in the budget settings or configuration, leading to discrepancies between the overall budget and the distributed budget.
- Data Entry Errors: Manual entries or incorrect postings can lead to an inflated distributed budget.
- Budget Release Issues: The budget may not have been properly released or updated, leading to inconsistencies.
Solution:
- Review Budget Allocation: Check the overall budget allocation for the relevant cost center or project. Ensure that it is sufficient to cover the distributed budget.
- Adjust Budget: If the overall budget is indeed less than the distributed budget, consider increasing the overall budget to accommodate the distributed amounts.
- Analyze Commitments: Review the commitments and actual expenditures to identify any erroneous entries or postings that may have contributed to the overcommitment.
- Correct Data Entries: If there are errors in data entry, correct them to reflect the accurate amounts.
- Budget Release: Ensure that the budget has been properly released and is active for the relevant period.
- Consult with Finance Team: If necessary, consult with your finance or budgeting team to understand the implications of changing budget figures and to ensure compliance with financial policies.
Related Information:
S_ALR_87013558
(Budget/Actual/Commitment) or S_ALR_87013559
(Budget Overview) to analyze budget data.By following these steps, you should be able to resolve the BQ001 error and ensure that your budget management processes are functioning correctly.
Get instant SAP help. Sign up for our Free Essentials Plan.
BP_ADDON104
Overall values are not allowed if source year <> target year
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
BP_ADDON103
The target year cannot be smaller than the source year
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
BQ002
- &: & <& (&)
What causes this issue? The total budget &V2& &V4& in WBS element &V1& is less than the distributed budget &V3& &...
BQ003
Annual budget & less than distributed budget
What causes this issue? Annual budget &V1& for one or more WBS elements is less than the distributed budget.System Response The system issue...