Message type: E = Error
Message class: BP - Budgeting and planning
Message number: 670
Message text: Budget profile can only be used when object currencies are the same
You set the availability control indicator in the object currency.
Availability control in object currency is only possible if all objects
in a budgeting hierarchy have the same object currency.
Check if your entry is correct.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
BP670
- Budget profile can only be used when object currencies are the same ?The SAP error message BP670 ("Budget profile can only be used when object currencies are the same") typically occurs in the context of budget management within SAP, particularly when dealing with budget profiles and currency settings. This error indicates that there is a mismatch in the currencies used for the budget profile and the object (e.g., cost center, internal order) to which the budget is being applied.
Cause: Currency Mismatch: The budget profile is set up in a specific currency, but the object (like a cost center or internal order) is in a different currency. SAP requires that both the budget profile and the object currency be the same to ensure accurate budget tracking and reporting.
Configuration Issues: The budget profile may not be configured correctly to handle multiple currencies, or the settings for the object may not align with the budget profile. Master Data Issues: The master data for the budget profile or
Get instant SAP help. Sign up for our Free Essentials Plan.
BP669
Reconstruct Availability Control
What causes this issue? You have <ZH>not</> carried out the necessary reconstruction of the availability control for certain objects afte...
BP668
Settings in budget profile of measures have been changed
What causes this issue? The settings for availability control in the budget profile were changed for at least one of your measures, or a different bu...
BP671
The object currencies in the budgeting hierarchy are not the same
What causes this issue? In the budget profile of project &V1&, you have set the availability control indicator in the object currency.System ...
BP672
Object currencies of && and WBS element & do not match
What causes this issue? In the budget profile of project &V4&, you have set the availability control in the object currency.System Response ...