Do you have any question about this error?
Message type: E = Error
Message class: BP - Budgeting and planning
Message number: 551
Message text: WBS element & is not a planning element
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
BP551
- WBS element & is not a planning element ?The SAP error message BP551 indicates that the Work Breakdown Structure (WBS) element you are trying to use is not recognized as a planning element. This typically occurs in the context of project management within SAP, particularly when dealing with project planning and budgeting.
Cause of Error BP551
- WBS Element Status: The WBS element may not be set up correctly or may not be in a status that allows it to be used for planning. For example, it might be in a "deleted" or "inactive" status.
- WBS Element Type: The WBS element might not be defined as a planning element in the system. Some WBS elements are created for reporting purposes and may not be intended for planning.
- Hierarchy Issues: The WBS element may not be properly linked within the project hierarchy, which can lead to it being unrecognized as a planning element.
- Authorization Issues: There may be authorization restrictions preventing the use of the WBS element for planning purposes.
Solution to Error BP551
Check WBS Element Status: Verify the status of the WBS element in the system. Ensure it is active and not marked for deletion.
- You can check this in transaction code
CJ20N
(Project Builder) orCJ03
(Display WBS Element).Review WBS Element Configuration: Ensure that the WBS element is configured correctly to be a planning element. This can involve checking the settings in the WBS element master data.
- Use transaction code
CJ02
(Change WBS Element) to review and modify the settings if necessary.Hierarchy Verification: Ensure that the WBS element is correctly positioned within the project hierarchy. If it is a child element, ensure that the parent element is also a planning element.
Authorization Check: Confirm that you have the necessary authorizations to use the WBS element for planning. You may need to consult with your SAP security team to ensure your user role has the appropriate permissions.
Consult Documentation: If the issue persists, refer to SAP documentation or consult with your SAP support team for further assistance.
Related Information
CJ20N
, CJ03
, CJ02
, and CJ01
for project management tasks.By following these steps, you should be able to identify the cause of the BP551 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
BP550
Enter WBS element, as there are a number of subprojects.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
BP549
*-----Messages 550 to 598 reserved for projects
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
BP552
Specify the project or a top WBS element of the project
What causes this issue? You want to plan a subhierarchy for project &V3&. In plan profile &V1& of project &V3&, the indicator...
BP570
Project & : Plan values reconstructed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...