Do you have any question about this error?
Message type: E = Error
Message class: AW - AuC messages
Message number: 251
Message text: You are not allowed to maintain settlement rules for network header
The network is activity assigned. In activity-assigned networks, you
may maintain settlement rules only for the individual activities.
Maintain the settlement rules for the individual activities.
Error message extract from SAP system. Copyright SAP SE.
AW251
- You are not allowed to maintain settlement rules for network header ?The SAP error message AW251 ("You are not allowed to maintain settlement rules for network header") typically occurs when a user attempts to maintain settlement rules for a network header in a project system (PS) or related module, but does not have the necessary authorizations or the system settings do not allow it.
Cause:
- Authorization Issues: The user may not have the required authorizations to maintain settlement rules for the network header. This is often controlled by user roles and profiles in SAP.
- Configuration Settings: The system may be configured in such a way that it restricts the maintenance of settlement rules for network headers.
- Network Header Status: The status of the network header may not allow changes to settlement rules. For example, if the network is already settled or in a locked state, changes may not be permitted.
Solution:
Check Authorizations:
- Verify the user's roles and authorizations in the SAP system. Ensure that the user has the necessary permissions to maintain settlement rules for network headers.
- You can use transaction code
SU53
to check for authorization failures after the error occurs.Review Configuration:
- Check the configuration settings related to the project system and settlement rules. Ensure that the settings allow for the maintenance of settlement rules for network headers.
- You may need to consult with your SAP Basis or configuration team to review these settings.
Network Header Status:
- Check the status of the network header. If it is in a status that does not allow changes (e.g., "Completed" or "Locked"), you may need to change the status or unlock it before making changes to the settlement rules.
- You can use transaction code
CN22
to check and change the status of the network.Consult Documentation:
- Refer to SAP documentation or help resources for more detailed information on settlement rules and network headers. This can provide insights into specific configurations or limitations.
Contact Support:
- If the issue persists after checking authorizations and configurations, consider reaching out to your SAP support team or SAP Help Desk for further assistance.
Related Information:
CN22
: Change NetworkCJ20N
: Project BuilderSU53
: Display Authorization CheckPFCG
to ensure they have the necessary access rights.By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
AW250
Default values for work breakdown structure are unreadable
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
AW235
The cost element for settlement of AuC to CO receiver is not maintained.
What causes this issue? You want to settle a line item to a CO receiver. For this settlement, there must be a cost element maintained in the account...
AW252
You are not allowed to maintain settlement rules for network activity
What causes this issue? The network is <ZH>not</> activity assigned.How to fix this error? Maintain the settlement rules for the network...
AW253
The object is not a cap. investment measure or has no asset u. const.
What causes this issue? You have selected an object, which is either not a capital investment measure, or to which, at least, no asset under construc...
Click on this link to search all SAP messages.