Message type: E = Error
Message class: AP - Investment program messages
Message number: 193
Message text: Subordinate WBS element is already assigned to a program position
You want to assign WBS element &V1& to an investment program position.
The system determined that WBS element &V2&, which is below your WBS
element in the hierarchy, is already assigned to an investment program
position.
In order to keep the hierarchy consistent, your assignment is not
allowed.
The assignment is rejected.
Error message extract from SAP system. Copyright SAP SE.
AP193
- Subordinate WBS element is already assigned to a program position ?The SAP error message AP193, which states "Subordinate WBS element is already assigned to a program position," typically occurs in the context of project management within SAP, particularly when dealing with Work Breakdown Structures (WBS) and program management.
Cause:
This error arises when you attempt to assign a subordinate WBS element to a program position that it is already associated with. In SAP, each WBS element can only be assigned to one program position at a time. If you try to assign it again, the system will prevent this action to maintain data integrity and avoid duplication.
Solution:
To resolve this error, you can take the following steps:
Check Current Assignments:
- Use transaction codes like
CJ20N
(Project Builder) orCJ03
(Display WBS) to check the current assignments of the WBS element. Verify if it is already assigned to another program position.Remove Existing Assignment:
- If the WBS element is indeed assigned to a program position that you do not need, you can remove the existing assignment. This can be done in the same transaction (e.g.,
CJ20N
) by navigating to the relevant program position and deleting the assignment.Reassign the WBS Element:
- After removing the existing assignment, you can then proceed to assign the WBS element to the desired program position.
Consult Documentation:
- If you are unsure about the implications of changing assignments, consult your project management documentation or speak with your project manager or SAP administrator.
Check for Dependencies:
- Ensure that there are no dependencies or constraints that might be affected by changing the assignment of the WBS element.
Related Information:
CJ20N
, CJ03
, CJ02
(Change WBS), and CJ01
(Create WBS) for managing WBS elements.By following these steps, you should be able to resolve the AP193 error and manage your WBS assignments effectively.
Get instant SAP help. Start your 7-day free trial now.
AP192
Next higher WBS element is already assigned to a program position
What causes this issue? You want to assign WBS element &V1& to an investment program position. The system determined that WBS element &V2...
AP191
Deletion flag or deletion indicator is set - assignment not possible
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
AP194
WBS element &1 is already budgeted or availability control is active
What causes this issue? You tried to attach WBS element &V1& to a program position. The settings for this program position specify that all W...