Do you have any question about this error?
Message type: E = Error
Message class: 7A - PS Progress Analysis
Message number: 312
Message text: Statistical key figure with usage &1 for POC not defined (IMG)
You want to save POCs. However, the settings in Customizing (IMG) are
not complete. You have not defined a statistical key figure with usage
&v1&.
Processing stopped.
Contact your system administrator.
Procedures for the system administrator:
For CO area &v2& create a statistical key figure with usage &v1&.
<DS:SIMG.SIMG_OLPR_EVSK>Execute</>
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
7A312
- Statistical key figure with usage &1 for POC not defined (IMG) ?The SAP error message 7A312 indicates that a statistical key figure (SKF) with a specific usage is not defined in the system for the purpose of Percentage of Completion (POC) accounting. This error typically arises in the context of project management and controlling, particularly when dealing with project-related costs and revenues.
Cause:
The error occurs when:
- A statistical key figure is referenced in a project or controlling document, but it has not been defined in the system.
- The statistical key figure is required for calculating the Percentage of Completion (POC) but is missing or incorrectly configured in the system.
Solution:
To resolve this error, you need to define the missing statistical key figure in the system. Here are the steps to do this:
Access the SAP IMG (Implementation Guide):
- Use transaction code
SPRO
to access the SAP Customizing Implementation Guide.Navigate to the Statistical Key Figures Configuration:
- Follow the path: Controlling -> General Controlling -> Statistical Key Figures -> Define Statistical Key Figures.
Define the Missing Statistical Key Figure:
- Check if the statistical key figure with the specified usage (indicated by &1 in the error message) is listed.
- If it is not defined, create a new statistical key figure by clicking on the "New Entries" button.
- Fill in the required fields, including the key figure name, description, and usage type.
Assign the Statistical Key Figure to the Relevant Objects:
- Ensure that the newly defined statistical key figure is assigned to the relevant cost centers, internal orders, or projects as needed.
Check for Consistency:
- After defining the SKF, check for any inconsistencies in the project or controlling documents that might still reference the missing SKF.
Test the Changes:
- Once the SKF is defined and assigned, try to execute the transaction or process that previously generated the error to confirm that the issue is resolved.
Related Information:
CJ20N
(Project Builder) and CJI3
(Project Actual Line Items) for project management tasks.If the issue persists after following these steps, it may be necessary to consult with your SAP support team or refer to SAP documentation for further troubleshooting.
Get instant SAP help. Start your 7-day free trial now.
7A311
No progress cost element (category 61) found for cost element &
What causes this issue? There are two differnet cases where this error occurs. The situation depends on the base for the earned value calculation: Co...
7A310
Cost element assignments not maintained
What causes this issue? The assignment of cost elements to progress cost elements has not been maintained.System Response The system is not able to ...
7A313
CO version &1 is can only be used as a progress version
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
7A314
Could not determine company code for plant &1 (IMG)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.