Do you have any question about this error?
Message type: E = Error
Message class: KP - CO-OM Planning
Message number: 253
Message text: Kostenstelle & Leistungsart &: Leistungsbezug bei Leistung 0
The SAP System cannot calculate activity prices as this would involve
division by zero. Activity input planning is threfore ignored in
activity price calculation.
Check plan activity price calculation planning for activity type &V2&,
cost center &V1& and the cost planning.
<DS:TRAN.KP26>Activity Type Planning</>
<DS:TRAN.KP17>Primary Cost Planning</>
For actual activity price calculation, actual costs are allocated onto
the activity type by splitting, although no activity posting has been
made to the activity type.
Fehlermeldungsextrakt aus SAP-System. Copyright SAP SE
KP253
- Kostenstelle & Leistungsart &: Leistungsbezug bei Leistung 0 ?Get instant SAP help. Start your 7-day free trial now.
KP252
Kostenstelle & Leistungsart &: Leistungsbezug bei Leistung 0
The plan activity for cost center &V1&, activity type &V2& is 0. However, activity input was planned for period(s) &V3&.Syste...
KP251
Kostenstelle & Leistungsart &: Kosten trotz Leistung 0
Was verursacht dieses Problem? The plan and posted activity for cost center &V1&, activity type &V2& is 0. However, costs were plan...
KP254
Es sind keine Leistungen gebucht worden
Was verursacht dieses Problem? No activity consumption was posted in controlling area &V1& in fiscal year &V2&.Systemantwort Actu...
KP255
Elementeschema zur Komponenteniteration nicht vorhanden
Was verursacht dieses Problem? Price calculation, according to the entry in version &V2&, should be carried out with component layering (co...
Klicken Sie auf diesen Link, um alle SAP-Meldungen durchsuchen.