Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 503
Message text: &1 : date de fin du composant située dans le passé (T4)
The finish date of the order proposals for the components is in the
past.
This exception message appears in the MRP list for a planning run in
the main memory. This situation can occur if automatic forward
scheduling in MRP is switched off in Customizing for the corresponding
plant.
Check whether the order proposals for the components are to be
rescheduled and/or converted. You can access these order proposals by
choosing the function 'Order structure' for the receipt you are
viewing.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
MD503
- &1 : date de fin du composant située dans le passé (T4) ?Get instant SAP help. Start your 7-day free trial now.
MD502
&1 : date de début du composant située dans le passé (T3)
Quelle est la cause de ce problème? The start date of order proposals for the components is in the past.Réponse du système This exception messag...
MD501
&1 : pas de couverture par le PDP au niveau du composant (S8)
Quelle est la cause de ce problème? After an ATP check, the system has determined that the requirements for the components are not covered by the m...
MD504
&1 : opération de préférence au niveau du composant (U1)
Quelle est la cause de ce problème? The rescheduling check has calculated that the receipts of the components are not available until too late of a...
MD505
&1 : décaler l'opération au niveau du composant (U2)
Quelle est la cause de ce problème? The rescheduling check has determined that the receipts for the components should be changed to avoid excessive...