Do you have any question about this error?
Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 427
Message text: &1 : &2 (P4)
The production finish date calculated using the routing lies after the
order finish date that was calculated using the in-house processing time
in the material master record.
As the system uses the order finish date in the planning run, this
situation may lead to material shortages if production is not finished
until the production finish date calculated by the system.
This exception is displayed in the MRP list and in the current
stock/requirements list.
Check the times in the material master record and in the routing.
Check whether the order has to be rescheduled in.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
MD427
- &1 : &2 (P4) ?Get instant SAP help. Start your 7-day free trial now.
MD426
&1 : &2 (P3)
Quelle est la cause de ce problème? In Customizing, no specification has been made to allow the adjustment of the order start date to the productio...
MD425
&1 : &2 (P2)
Quelle est la cause de ce problème? The system could not find a valid routing when scheduling via the routing or the routing is incorrect.Réponse ...
MD428
&1: &2 (S9)
Quelle est la cause de ce problème? The following reasons exist: Either a component of the planned order or production order entered is identical t...
MD429
&1: &2 (U6)
Quelle est la cause de ce problème? In the individual segment (make-to-order planning, individual project planning, or direct production or direct ...
Cliquez sur ce lien pour rechercher tous les messages SAP.