How To Fix MD411 - &1 : &2 (S7)


SAP Error Message - Details

  • Message type: E = Error

  • Message class: MD - Material Requirements Planning (MRP)

  • Message number: 411

  • Message text: &1 : &2 (S7)

  • Show details Hide details
  • Quelle est la cause de ce problème?

    In the MRP list, this exception message is set if an shortage occurs
    within the planning time fence for a material with fixing type '2' or
    '4'.
    No order proposals are created in the planning run for shortages within
    the planning time fence for these fixing types.
    The system also does not balance the possible shortage by creating
    order proposals at the end of the planning time fence.
    Special case: direct production (collective order):
    The exception is set irrespective of the fixing type if a material
    shortage has occurred for an existing collective order.

    Le système émet un message d'erreur et ne vous permettra pas de poursuivre cette transaction tant que l'erreur n'est pas résolue.

    Réponse du système

    This exception message is displayed in the MRP list.

    Comment corriger cette erreur?

    You have to plan manually within the planning time fence for MRP types
    with fixing type '2' or '4'.
    Therefore, the MRP controller must take appropriate measures to balance
    shortages.

    Extrait du message d'erreur du système SAP. Copyright SAP SE.


Smart SAP Assistant

  • Quelle est la cause et la solution de l'erreur SAP MD411 - &1 : &2 (S7) ?




    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Messages d'erreur SAP associés

Cliquez sur les liens ci-dessous pour voir les messages connexes suivants:
  • MD410 &1 : &2 (S6)
    Quelle est la cause de ce problème? This exception message is set in the MRP list if a requirement exists outwith the effective out date for a part...

  • MD409 &1 : &2 (S3)
    Quelle est la cause de ce problème? No valid run schedule header could be selected for the planned order (run schedule quantity) of a material that...

  • MD412 &1 : &2 (S8)
    Quelle est la cause de ce problème? During the availability check with ATP logic, the system determined that this requirement is not covered by the...

  • MD413 &1 : &2 (T2)
    Quelle est la cause de ce problème? The opening date of the order proposal or purchase order lies in the past.Réponse du système This exception ...

Cliquez sur ce lien pour rechercher tous les messages SAP.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author