Message type: E = Error
Message class: CP - Task list messages: Core data
Message number: 324
Message text: Séquence &/&/& : numéro d'opération incorrect
The number of the first operation in sequence &V3& of task list &V1&
&V2& is less than the number of the branch operation in the standard
sequence.
However, the first operation in alternative or parallel sequences
must have a number greater than the number of the operation before the
branch operation in the standard sequence.
Check the task list and
correct the operation numbers in sequence &V3&
<ZH>or</>
correct the operation numbers in the standard sequence.
Extrait du message d'erreur du système SAP. Copyright SAP SE.
Get instant SAP help. Sign up for our Free Essentials Plan.
CP323 Séquence &/&/& : opération de sortie > opération de retour
Quelle est la cause de ce problème? In sequence &V3& of group &V1&, group counter &V2&, the number of the branch operation ...
CP322 L'opération de retour dans la séquence &/&/& n'existe pas
Quelle est la cause de ce problème? The return operation of sequence &V3& in group &V1&, group counter &V2& does not exist ...
CP325 Séquence &/&/& : numéro d'opération incorrect
Quelle est la cause de ce problème? The number of the last operation in sequence &V3& of task list &V1& &V2& is greater tha...
CP326 Gamme supprimée
Quelle est la cause de ce problème? The system will not process this routing any further because the group counter &V2& in group &V1&am...
Cliquez sur ce lien pour rechercher tous les messages SAP.