Do you have any question about this error?
Message type: E = Error
Message class: HRHCP00_PLAN - Messages About Personnel Cost Plan
Message number: 095
Message text: Error al implementar BAdI; período del componente del coste no válido
The derived and additional cost items were changed in an implementation
of the BAdI HRHCP00_DERIVE_VALU with the method
CHANGE_DERIVED_COSTITEMS. The return table contains cost items whose
period exceeds the validity of the object. The cost object is valid
from &V3& to &V4&, but a cost item exists that is valid from &V1& to
&V2&.
The system does not process these cost items any further.
El sistema emite un mensaje de error y no le permitirá continuar con esta transacción hasta que se resuelva el error.
Check the BAdI implementation.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
HRHCP00_PLAN095
- Error al implementar BAdI; período del componente del coste no válido ?Get instant SAP help. Start your 7-day free trial now.
HRHCP00_PLAN094
Error al implementar BAdI; períodos solapados
¿Qué causa este problema? You have used the method &V1& of BAdI HRHCP00_DERIVE_VALU to determine the organizational grouping of cost object...
HRHCP00_PLAN093
Error al implementar el BAdI; períodos discontinuos
¿Qué causa este problema? In the enhancement (BAdI) HRHCP00_POST_PERIODS the posting periods have been changed. Since this change the posting perio...
HRHCP00_PLAN096
Error al implementar BAdI; asignación falsa a imputación diferente
¿Qué causa este problema? The derived and additional cost items were changed in an implementation of the BAdI HRHCP00_DERIVE_VALU with the method C...
HRHCP00_PLAN097
Error al implementar BAdI; período no válido
¿Qué causa este problema? The object selection for the planning run was changed in an implementation of the BAdI HRHCP00_RUN_OBJSEL. The return tab...