Message type: E = Error
Message class: CY - Capacity Requirements Planning
Message number: 727
Message text: & no tiene enlace con sucesor & en grafo recursos & en centro &
The header data of the process order specifies that the operations must
be scheduled on a particular resource network structure.
However, the operation has been scheduled on a resource that is not
defined as a predecessor resource of the resource on which a "successor"
operation is to be carried out.
Please schedule the operations in the sequence defined by the resource
network structure.
Extracto de mensaje de error del sistema SAP. Copyright SAP SE.
CY727
- & no tiene enlace con sucesor & en grafo recursos & en centro & ?Get instant SAP help. Start your 7-day free trial now.
CY726
& no tiene enlace con el antecesor & en grafo de recursos & en centro &
¿Qué causa este problema? The header data of the process order specifies that the operations must be scheduled on a particular resource network str...
CY725
& no pertenece al grafo de recursos & en centro &
¿Qué causa este problema? The header data of the process order specifies that the operations on resource network structure &V2& are to be s...
CY728
Orden & operación &: no se cumple el solapamiento mínimo con antecesor &
¿Qué causa este problema? On dispatching an operation the system does not adhere to the minimum overlap time with the preceding operation. There wa...
CY729
Orden & operación &: no se cumple el solapamiento mínimo con sucesor &
¿Qué causa este problema? When dispatching an operation the system does not adhere to the minimum overlap time with the following operation. There ...