Stop googling SAP errors. Use our Free Essentials plan instead - no credit card needed. Start Now

Close

How To Fix VL291 - Goods issue date &1 at &2 set; &3 at &4 was planned in the schedule line


SAP Error Message - Details

  • Message type: E = Error

  • Message class: VL -

  • Message number: 291

  • Message text: Goods issue date &1 at &2 set; &3 at &4 was planned in the schedule line

  • Show details Hide details
  • What causes this issue?

    Goods issue date was changed to &V1& at &V2&. In the order item
    schedule line, goods issue was planned for &V3& at &V4&.

    System Response

    The system rescheduled the shipping deadlines.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message VL291 - Goods issue date &1 at &2 set; &3 at &4 was planned in the schedule line ?

    The SAP error message VL291 indicates that there is a discrepancy between the goods issue date and the planned delivery dates in the schedule line of a sales order or delivery. This error typically arises when the system detects that the goods issue date does not align with the expected delivery dates for the items in the schedule line.

    Cause:

    1. Mismatch in Dates: The goods issue date specified in the delivery document does not match the planned delivery date in the schedule line.
    2. Incorrect Configuration: There may be issues with the configuration of the delivery dates in the material master or sales order.
    3. Changes in Delivery Dates: If the delivery dates were changed after the schedule line was created, it could lead to this error.
    4. Planning Parameters: The planning parameters for the material or the sales order may not be set correctly, leading to inconsistencies.

    Solution:

    1. Check Dates: Review the goods issue date and the planned delivery dates in the schedule line. Ensure that they are consistent and correct.
    2. Adjust Schedule Line: If necessary, adjust the schedule line to match the goods issue date. This can be done in the sales order or delivery document.
    3. Review Configuration: Check the configuration settings for the material and sales order to ensure that they are set up correctly for delivery dates.
    4. Recreate Delivery: If the issue persists, consider recreating the delivery document after ensuring that all dates are aligned correctly.
    5. Consult Documentation: Refer to SAP documentation or consult with your SAP support team for specific configuration settings that may need to be adjusted.

    Related Information:

    • Transaction Codes: You may need to use transaction codes like VL02N (Change Outbound Delivery) or VA02 (Change Sales Order) to make necessary adjustments.
    • SAP Notes: Check for any relevant SAP Notes that may address this specific error or provide additional guidance.
    • User Exits and BAdIs: If custom logic is implemented, review any user exits or BAdIs that may affect the delivery date calculations.

    By following these steps, you should be able to resolve the VL291 error and ensure that the goods issue date aligns with the planned delivery dates in the schedule line.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating