Message type: E = Error
Message class: T1 - Financial instruments
Message number: 211
Message text: 'Start of lead time' later than 'End of hedging period'
You have entered a date for the 'Start of lead time' that is later than
the 'End of hedging period'.
Enter an earlier date for the 'Start of lead time' than the date for
the 'End of hedging period'.
Error message extract from SAP system. Copyright SAP SE.
T1211
- 'Start of lead time' later than 'End of hedging period' ?The SAP error message T1211, which states that the "Start of lead time" is later than the "End of hedging period," typically occurs in the context of materials planning and procurement processes. This error indicates a mismatch in the timing of the lead time for procurement or production and the defined hedging period for a material.
Cause:
Lead Time Configuration: The lead time for a material (the time required to procure or produce the material) is set to start after the hedging period has ended. This can happen if the lead time is incorrectly configured in the material master or if the hedging period is not aligned with the procurement process.
Hedging Period Definition: The hedging period is defined in the system to manage price fluctuations and ensure that procurement is done within a certain timeframe. If the lead time exceeds this period, the system will throw this error.
Planning Parameters: Incorrect planning parameters or settings in the material master or in the planning strategy can lead to this error.
Solution:
Review Material Master Data: Check the material master data for the specific material causing the error. Ensure that the lead time is set correctly and that it aligns with the hedging period.
Adjust Lead Time: If the lead time is indeed longer than the hedging period, consider adjusting the lead time to ensure it starts and ends within the hedging period.
Modify Hedging Period: If the lead time is correct and cannot be shortened, you may need to extend the hedging period to accommodate the lead time.
Check Planning Strategy: Review the planning strategy used for the material. Ensure that it is appropriate for the type of procurement and production processes in place.
Consult Documentation: Refer to SAP documentation or consult with your SAP support team for specific configuration settings related to lead times and hedging periods.
Testing: After making adjustments, perform testing to ensure that the error is resolved and that the procurement process functions as expected.
Related Information:
By addressing the configuration of lead times and hedging periods, you should be able to resolve the T1211 error and ensure smooth material planning and procurement processes.
Get instant SAP help. Sign up for our Free Essentials Plan.
T1210
Premium has no payment date
What causes this issue? You did not enter all the required data for creating a premium.How to fix this error? Enter the following data: 'Effect...
T1209
Expiration period is exceeded
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
T1212
'Start of lead time' same as 'Start of hedging period'
What causes this issue? In the 'Start of lead time' field, you have entered the same date as the 'Start of hedging period'. This ...
T1213
'Start of hedging period' later than/same as 'End of hedging period'
What causes this issue? In the 'Start of hedging period' field, you have entered a date which is either the same or later than that in the ...
Click on this link to search all SAP messages.