Message type: E = Error
Message class: SI - Implementation Guide - Status control
Message number: 081
Message text: Planned start & is earlier than project start date &
You specified a planned starting date which is before the project
start time &V2&. The planned starting date must be the same as or
after the project start time &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Enter a planned starting date from the &V2&.
Otherwise, change the project start time:
INCLUDE 'NA_STATUS_PROJECT_MAINT' OBJECT DOKU ID TX
Error message extract from SAP system. Copyright SAP SE.
SI081
- Planned start & is earlier than project start date & ?The SAP error message SI081 indicates that there is a discrepancy between the planned start date of a task or activity and the project start date. Specifically, it means that the planned start date is set earlier than the project's defined start date, which is not allowed in SAP Project System (PS).
Cause:
- Incorrect Date Entry: The planned start date for a task or activity has been entered incorrectly, leading to it being set before the project's start date.
- Project Configuration: The project itself may have been configured with a start date that does not align with the planned activities.
- Changes in Project Timeline: If the project start date was changed after the planned dates were set, this could lead to inconsistencies.
Solution:
- Check Project Dates: Verify the project start date in the project definition. Ensure that it is set correctly and reflects the intended start of the project.
- Adjust Planned Start Date: Modify the planned start date of the task or activity to ensure it is on or after the project start date. This can typically be done in the project planning screen.
- Review Dependencies: If the task is dependent on other tasks or milestones, ensure that those dependencies are correctly set and that they do not conflict with the project start date.
- Re-evaluate Project Schedule: If there are multiple tasks with planned dates, consider reviewing the entire project schedule to ensure all dates are aligned properly.
Related Information:
CJ20N
(Project Builder) or CJ02
(Change Project) to access and modify project details.If the issue persists after making the necessary adjustments, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in SAP Project System for further assistance.
Get instant SAP help. Start your 7-day free trial now.
SI080
At least 1 project must be chosen
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
SI079
****** Reserved for DDIC foreign key ************************************
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
SI082
Planned end date & is later than project end date &
What causes this issue? You have entered a plan end, which is after the project end date &V2&. The plan end must not be later than the projec...
SI083
Planned start & is after project end date &
What causes this issue? You have entered a plan begin which is after the project end date &V2&. The plan begin must be before the project end...
Click on this link to search all SAP messages.