How To Fix SI083 - Planned start & is after project end date &


SAP Error Message - Details

  • Message type: E = Error

  • Message class: SI - Implementation Guide - Status control

  • Message number: 083

  • Message text: Planned start & is after project end date &

  • Show details Hide details
  • What causes this issue?

    You have entered a plan begin which is after the project end date
    &V2&. The plan begin must be before the project end.

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?

    Enter a plan begin which is before &V2&.
    Otherwise, you must change the project end date:
    INCLUDE 'NA_STATUS_PROJECT_MAINT' OBJECT DOKU ID TX

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message SI083 - Planned start & is after project end date & ?

    The SAP error message "SI083 Planned start & is after project end date &" typically occurs in project management modules when there is a mismatch between the planned start date of a task or activity and the defined end date of the project. This error indicates that the planned start date for a specific task is set to a date that is later than the project's end date, which is not permissible.

    Cause:

    1. Incorrect Date Entry: The planned start date for a task or activity has been entered incorrectly, leading to it being set after the project's end date.
    2. Project End Date Misconfiguration: The project end date may have been set incorrectly or may not reflect the actual timeline of the project.
    3. Changes in Project Timeline: If the project timeline has been adjusted (e.g., extended or shortened) after tasks were created, it may lead to inconsistencies.
    4. Data Migration Issues: If data was migrated from another system, there may be discrepancies in date formats or values.

    Solution:

    1. Check Planned Start Date: Review the planned start date of the task or activity that is causing the error. Ensure that it is set to a date that is on or before the project end date.
    2. Review Project End Date: Verify the project end date in the project definition. If the project timeline has changed, update the project end date accordingly.
    3. Adjust Task Dates: If the project end date is correct, adjust the planned start date of the task to ensure it falls within the project timeline.
    4. Consult Project Documentation: Review any project documentation or planning materials to ensure that the dates align with the overall project schedule.
    5. Use SAP Transaction Codes: Utilize relevant SAP transaction codes (like CJ20N for project management) to navigate to the project and task details for adjustments.
    6. Check Dependencies: Ensure that there are no dependencies or constraints that might be affecting the planned start date.

    Related Information:

    • SAP Documentation: Refer to SAP Help documentation for project management to understand how dates are managed within the system.
    • User Roles and Permissions: Ensure that you have the necessary permissions to make changes to project dates.
    • Testing Changes: After making adjustments, test the changes in a development or test environment before applying them in production to avoid further issues.
    • Consult with Project Managers: If you are unsure about the correct dates, consult with project managers or stakeholders involved in the project for clarification.

    By following these steps, you should be able to resolve the error and ensure that the project and task dates are correctly aligned.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant