Message type: E = Error
Message class: /SAPAPO/CTM1 -
Message number: 347
Message text: Plan &1 has more than one activity without predecessors
Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of messages in the SAP system have a message text, however this is frequently insufficient to comprehend or resolve the problem.
To make things easier, more detailed information is frequently added to describe the issue, how to fix it, and the necessary steps or configuration modifications.
Unfortunately, there isn't any extra information in this error notice.
First, use our AnswerBot below to get a possible cause and solution (requires a premium subscription).
Also, review the in-depth Common Questions & Answers listed below; you could discover a solution there or be able to connect with others who have faced similar challenges.
You can also try searching the SAP support portal (support.sap.com) but you need a special user ID to access it. It is possible that an SAP support note exists that provides additional details about the mistake or even steps for fixing it.
/SAPAPO/CTM1347
- Plan &1 has more than one activity without predecessors ?The SAP error message /SAPAPO/CTM1347 Plan &1 has more than one activity without predecessors typically occurs in the context of SAP Advanced Planning and Optimization (APO), particularly when using the Capacity Planning or CTM (Capable-to-Match) functionalities. This error indicates that there is a planning object (like a production plan) that has multiple activities that do not have any predecessor activities defined. This situation can lead to ambiguity in the planning process, as the system does not know the order in which these activities should be executed.
Cause: Multiple Activities Without Predecessors: The primary cause of this error is that the planning object has more than one activity that can start independently, which can create conflicts in scheduling. Incorrect Activity Configuration: The activities may not be properly configured in terms of their relationships, leading to a lack of defined predecessors. Data Integrity Issues: There may be issues with the data integrity in the planning object,
Get instant SAP help. Sign up for our Free Essentials Plan.
/SAPAPO/CTM1346
Plan &1 has more than one activity without successors
What causes this issue? The CTM master data check issues this message in the following cases: The PPM has parallel activities without successors. Som...
/SAPAPO/CTM1345
Plan &1: Activity &2 has more than one predecessor
What causes this issue? CTM planning only supports PPMs with activities arranged in a linear fashion. Parallel activities are not supported.System Re...
/SAPAPO/CTM1348
No data found for resource &1
What causes this issue? In the current PPM you are using a resource for which CTM planning could not determine any data.System Response The system i...
/SAPAPO/CTM1349
Resource must have 100% capacity load
What causes this issue? In CTM planning a resource with a capacity level <> 100& is to be used.System Response As CTM currently only suppo...