How To Fix PPH_MRP168 - Period lot sizes only supported for one period


PPH_MRP168 - Overview

  • Message type: E = Error

  • Message class: PPH_MRP -

  • Message number: 168

  • Message text: Period lot sizes only supported for one period

  • Show details Hide details
  • What causes this issue?

    Your Customizing settings for lot sizing have been configured in such a
    way that the requirements of several days, weeks, or months are to be
    grouped together. However, MRP Live on SAP HANA does not support this
    type of period lot-sizing procedures where several periods are grouped
    together.
    In classic MRP, the system uses the first shortage date as the period
    start date. It then groups the requirements of the following "n" periods
    based on this date. Since shortages of different materials can exist on
    different days, it is possible that different groupings exist for each
    material.
    In MRP Live on SAP HANA, the system plans materials simultaneously
    instead of sequentially. As a result, it is not possible to define
    periods based on individual materials.

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    System Response

    If a period lot-sizing procedure has been defined for a material in
    Customizing and several periods are to be grouped together, the MRP Live
    report plans the material using classic MRP.

    How to fix this error?

    If system performance is affected by planning in classic MRP, change the
    lot-sizing procedure to one that is supported by MRP Live on SAP HANA.
    For example, you want to group requirements in quarterly periods.
    Instead of using a period lot-sizing procedure that groups three monthly
    periods, you create a planning calendar with periods starting on the
    January 1, April 1, July 1, and October 1.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


PPH_MRP168 - Details

  • The SAP error message PPH_MRP168 ("Period lot sizes only supported for one period") typically occurs in the context of Material Requirements Planning (MRP) when there is an issue with the configuration of lot sizing in the planning parameters for a material. This error indicates that the system is trying to apply a period lot size configuration that is not valid for the specified planning horizon.
    
    Cause: Lot Size Configuration: The error usually arises when the lot size settings for a material are configured to use a period lot size, but the planning parameters or the MRP run is set up in such a way that it expects a different configuration. Planning Horizon: If the planning horizon is set to more than one period, and the lot size is defined as a period lot size, the system cannot process this correctly, leading to the error. MRP Type: The MRP type assigned to the material may

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


PPH_MRP168 - Related SAP Errors

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker