How To Fix PPEFLO112 - Line resource &1 is already assigned to &2 &3


SAP Error Message - Details

  • Message type: E = Error

  • Message class: PPEFLO - Messages for iPPE Application Object FLO

  • Message number: 112

  • Message text: Line resource &1 is already assigned to &2 &3

  • Show details Hide details
  • What causes this issue?

    Line resource &V1& is already assigned to &V2& &V3&. A line resource
    cannot be assigned to several line nodes.

    System Response

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.

    How to fix this error?

    Either assign a different line resource, or delete the line node to
    which the resource is already assigned if it is no longer needed.

    Procedure for System Administrators


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message PPEFLO112 - Line resource &1 is already assigned to &2 &3 ?

    The SAP error message PPEFLO112 indicates that a line resource (such as a machine, tool, or labor resource) is already assigned to another operation or task in the production planning or scheduling process. This typically occurs in the context of production orders, process orders, or similar scenarios where resources are allocated to specific tasks.

    Cause:

    1. Resource Conflict: The line resource you are trying to assign is already in use for another operation or task at the same time.
    2. Scheduling Overlap: The time slots for the resource are overlapping with another assignment, leading to a conflict.
    3. Incorrect Configuration: There may be issues with the configuration of the resource or the production order that prevent proper assignment.

    Solution:

    1. Check Resource Availability: Verify the availability of the line resource in the system. You can do this by checking the resource's schedule to see if it is indeed assigned to another task.
    2. Adjust Scheduling: If the resource is busy, consider rescheduling the operation that requires the resource. This may involve changing the start or end times of the conflicting operations.
    3. Release Resource: If the resource is incorrectly assigned, you may need to release it from the current assignment before reassigning it to the desired operation.
    4. Review Resource Configuration: Ensure that the resource is correctly configured in the system and that there are no restrictions or settings that could be causing the conflict.
    5. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing resources and resolving conflicts.

    Related Information:

    • Transaction Codes: You may use transaction codes like CO02 (Change Production Order) or CO03 (Display Production Order) to check the status of production orders and their assigned resources.
    • Resource Planning: Familiarize yourself with resource planning concepts in SAP, including capacity planning and scheduling.
    • SAP Notes: Check for any relevant SAP Notes that may address known issues or provide additional troubleshooting steps related to this error message.

    If the issue persists after trying the above solutions, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and scheduling.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo's SAP support assistant is amazing. Saves me countless hours trying to solve complex SAP issues myself. It's a real game changer!
Rate 1
Thomas Michael
SAP Consultant, Author & Speaker