Message text: Line resource &1 is already assigned to &2 &3
Line resource &V1& is already assigned to &V2& &V3&. A line resource
cannot be assigned to several line nodes.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Either assign a different line resource, or delete the line node to
which the resource is already assigned if it is no longer needed.
Error message extract from SAP system. Copyright SAP SE.
PPEFLO112
- Line resource &1 is already assigned to &2 &3 ?The SAP error message PPEFLO112 indicates that a line resource (such as a machine, tool, or labor resource) is already assigned to another operation or task in the production planning or scheduling process. This typically occurs in the context of production orders, process orders, or similar scenarios where resources are allocated to specific tasks.
Cause:
- Resource Conflict: The line resource you are trying to assign is already in use for another operation or task at the same time.
- Scheduling Overlap: The time slots for the resource are overlapping with another assignment, leading to a conflict.
- Incorrect Configuration: There may be issues with the configuration of the resource or the production order that prevent proper assignment.
Solution:
- Check Resource Availability: Verify the availability of the line resource in the system. You can do this by checking the resource's schedule to see if it is indeed assigned to another task.
- Adjust Scheduling: If the resource is busy, consider rescheduling the operation that requires the resource. This may involve changing the start or end times of the conflicting operations.
- Release Resource: If the resource is incorrectly assigned, you may need to release it from the current assignment before reassigning it to the desired operation.
- Review Resource Configuration: Ensure that the resource is correctly configured in the system and that there are no restrictions or settings that could be causing the conflict.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on managing resources and resolving conflicts.
Related Information:
CO02
(Change Production Order) or CO03
(Display Production Order) to check the status of production orders and their assigned resources.If the issue persists after trying the above solutions, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in production planning and scheduling.
Get instant SAP help. Start your 7-day free trial now.
PPEFLO111
Resource &1 is not a line resource
What causes this issue? The assigned resource is not of the type 'line resource'.System Response The system issues an error message and wi...
PPEFLO110
Assign &1 &2 to a line resource
What causes this issue? There is no line resource assigned to the line node &V1& &V2&.System Response The system issues an error mes...
PPEFLO113
Node &1 does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEFLO114
&1 between &2 and &3 will be created when you save
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.