Message type: E = Error
Message class: PPEACT - Messages for iPPE ACT Application (Activities)
Message number: 625
Message text: The assigned activity &1 does not belong to the routing of assignmnt list
The activity that you have just assigned does not belong to the routing
that was selected in the assignment list.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Delete the assignment.
Error message extract from SAP system. Copyright SAP SE.
PPEACT625
- The assigned activity &1 does not belong to the routing of assignmnt list ?The SAP error message PPEACT625 indicates that there is a mismatch between the assigned activity and the routing in the assignment list. This typically occurs in the context of production planning or process order management, where activities are assigned to specific routings for production processes.
Cause:
- Incorrect Activity Assignment: The activity you are trying to assign does not exist in the routing for the specific production order or assignment list.
- Routing Changes: The routing may have been changed or updated, and the activity you are trying to assign is no longer part of the updated routing.
- Data Entry Errors: There may be a typographical error or incorrect selection when assigning the activity.
- Configuration Issues: There could be issues with the configuration of the routing or the activity types in the system.
Solution:
Verify Routing: Check the routing associated with the production order or assignment list to ensure that the activity you are trying to assign is indeed part of that routing.
- Use transaction code
CA03
to display the routing and confirm the activities listed.Update Assignment: If the activity is not part of the routing, you may need to either:
- Change the activity to one that is valid for the routing.
- Update the routing to include the required activity if it is necessary for the production process.
Check for Changes: If the routing has been recently changed, ensure that all relevant production orders or assignment lists are updated accordingly.
Consult Documentation: Review any documentation or guidelines related to the production process to ensure that the correct activities are being assigned.
Contact Support: If you are unable to resolve the issue, consider reaching out to your SAP support team or a consultant for further assistance.
Related Information:
CA03
(Display Routing), CO02
(Change Production Order), and C223
(Maintain Activity Types).By following these steps, you should be able to identify the cause of the error and implement a solution to resolve it.
Get instant SAP help. Start your 7-day free trial now.
PPEACT624
Assignment cannot be deleted because it is not assigned to an activity
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT623
No iPPE routing is assigned to the access
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT626
The product structure &1 &2 &3 &4 does not exist
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PPEACT627
Only mode linkage is allowed between primary resources under &1 &2
What causes this issue? A mode linkage using primary resources is required for the relationships between the activities below the operation.System Re...
Click on this link to search all SAP messages.