Do you have any question about this error?
Message type: E = Error
Message class: PMMO_PEGGING - Messages for Pegging in PMMO
Message number: 044
Message text: Missing master data for underpegged WBS - grouping WBS &1, MRP area &2
Missing master data for underpegged WBS element for account assignment
group &V1& and MRP area &V2&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Add the missing master data using the transaction
<DS:TRAN.PMMO_PEGEXC>Assign Exceptions.</>
INCLUDE PMMO_MMI_CUSTOMIZABLE_MSG OBJECT DOKU ID TX LANGUAGE EN
Error message extract from SAP system. Copyright SAP SE.
PMMO_PEGGING044
- Missing master data for underpegged WBS - grouping WBS &1, MRP area &2 ?The SAP error message PMMO_PEGGING044 indicates that there is missing master data for an underpegged Work Breakdown Structure (WBS) element. This typically occurs in the context of project management and material requirements planning (MRP) when the system is unable to find the necessary data to perform pegging for a specific WBS element and MRP area.
Cause:
Missing Master Data: The most common cause of this error is that the required master data for the specified WBS element or MRP area is not maintained in the system. This could include missing or incomplete data in the following areas:
- WBS element configuration
- MRP area settings
- Material master data
- Project definitions
Incorrect Configuration: There may be incorrect settings in the project or MRP area that prevent the system from recognizing the relationship between the WBS and the materials.
Data Inconsistencies: There could be inconsistencies in the data that lead to the system being unable to link the WBS to the required materials.
Solution:
Check WBS Element: Verify that the WBS element specified in the error message is correctly defined and that all necessary attributes are filled out. Ensure that it is active and properly linked to the project.
Review MRP Area Settings: Ensure that the MRP area associated with the WBS element is correctly configured. Check if the MRP area exists and is properly assigned to the relevant materials.
Maintain Master Data:
- Go to the material master and ensure that the relevant data for the materials linked to the WBS is complete.
- Check if the MRP views are maintained for the materials in question.
Check Project Definition: Ensure that the project definition is correctly set up and that all necessary components are linked to the WBS.
Run Consistency Checks: Use transaction codes like CJ20N (Project Builder) or CJI3 (Project Actual Line Items) to check for inconsistencies in the project structure and data.
Consult Documentation: Review SAP documentation or help resources for specific guidance on the error message and related configurations.
Related Information:
By following these steps, you should be able to identify and resolve the underlying issues causing the PMMO_PEGGING044 error in SAP.
Get instant SAP help. Start your 7-day free trial now.
PMMO_PEGGING043
Replenishment elem. &2 not pegged because no assignments found for NHA &1
What causes this issue? The replenishment element &v2& was not pegged because no assignments were found for the next higher assembly &v1&...
PMMO_PEGGING042
No extended memory available for pegging process
What causes this issue? The main pegging process is (or the pegging parallel sessions are) requesting extended memory for their processing.System Res...
PMMO_PEGGING101
Grouping WBS element &2 requires &1 to be included in the current run
What causes this issue? The selected grouping &V2& has a related higher-level grouping &V1&. However, &V1& is not included in...
PMMO_PEGGING102
No valid material number was found for the selection
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.