Do you have any question about this error?
Message type: E = Error
Message class: PK - Production - KANBAN
Message number: 304
Message text: The replenishment strategy no longer corresponds to the data entered
The replenishment strategy of this control cycle has been subsequently
changed. The indicator "from other plant" in Customizing in the
replenishment strategy, with which the control cycle was created, has
been deleted.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
You have the following options:
You leave the control cycle maintenance with "cancel", go to kanban
Customizing and there reset the indicator "from other plant" in the
control cycle replenishment strategy.
In the control cycle maintenance select a new replenishment strategy
for this control cycle.
You no longer want a cross-plant control cycle but you still want to
maintain it with the same strategy. In this case you retain the
current replenishment strategy and must simply save the crontol cycle
on leaving the control cycle maintenance.
Error message extract from SAP system. Copyright SAP SE.
PK304
- The replenishment strategy no longer corresponds to the data entered ?The SAP error message PK304, which states "The replenishment strategy no longer corresponds to the data entered," typically occurs in the context of inventory management and material requirements planning (MRP) when there is a mismatch between the replenishment strategy defined for a material and the data that has been entered for that material.
Causes:
- Inconsistent Data: The replenishment strategy defined in the material master may not align with the data entered in the planning parameters, such as lot size, safety stock, or reorder point.
- Changes in Configuration: If there have been recent changes to the replenishment strategy configuration in the system, it may not be compatible with existing data.
- Material Master Issues: The material master record may have incorrect or incomplete information, leading to inconsistencies.
- Planning Parameters: The planning parameters set for the material may not be appropriate for the selected replenishment strategy.
Solutions:
Review Material Master Data: Check the material master record for the material in question. Ensure that the replenishment strategy is correctly defined and that all relevant fields are filled out correctly.
- Transaction Code: MM03 (Display Material)
Check Replenishment Strategy: Verify that the replenishment strategy assigned to the material is appropriate for the data entered. If necessary, change the replenishment strategy to one that matches the data.
- Transaction Code: MM02 (Change Material)
Adjust Planning Parameters: Review and adjust the planning parameters such as lot size, safety stock, and reorder point to ensure they are compatible with the replenishment strategy.
- Transaction Code: MD02 (Single Item, Single Level Planning)
Consult Configuration Settings: If there have been recent changes to the configuration of replenishment strategies, consult with your SAP configuration team to ensure that the settings are correct and that they align with business processes.
Run MRP Again: After making the necessary adjustments, run the MRP process again to see if the error persists.
Check for User Exits or BAdIs: If custom logic is implemented in the system, check for any user exits or BAdIs that might be affecting the replenishment strategy.
Related Information:
If the issue persists after following these steps, it may be beneficial to consult with your SAP support team or a functional consultant who specializes in MRP and inventory management.
Get instant SAP help. Start your 7-day free trial now.
PK303
Distribution key specification missing in kanban calculation profile &1
What causes this issue? You have entered a calculation profile in the control cycle that smooths the requirements using a distribution function. The ...
PK302
Please enter a numerical value (greater than or equal to zero)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
PK305
This replen. strat. does not allow you to assign outline agt to an accnt
What causes this issue? You have chosen a replenishment strategy, with which material withdrawal is posted to the cost center. Your outline agreement...
PK306
Set the bulk material indicator in the material master
What causes this issue? You have selected a replenishment strategy with material consumption <LS>to cost center</>. For this strategy, th...