Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 680
Message text: Relationship & defined twice (Please check)
You have entered a relationship with the same type for the same
activity several times in field <ZH>predecessor </> or <ZH>successor</>
in Microsoft Project (R).
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
INCLUDE 'NA_ALLG_MOEGLICH' OBJECT DOKU ID TX
RESET N1
Correct the relationship in the MPX file.
Call up the MPX file in Microsoft Project (R) and correct the
relationship. Recreate the MPX file.
Error message extract from SAP system. Copyright SAP SE.
PJ680
- Relationship & defined twice (Please check) ?The SAP error message PJ680 ("Relationship & defined twice (Please check)") typically occurs in the context of project management within SAP, particularly when dealing with project structures and relationships between different elements (like WBS elements, activities, etc.). This error indicates that a relationship has been defined more than once for the same project element, which is not allowed.
Cause:
- Duplicate Relationships: The most common cause of this error is that the same relationship type (e.g., Finish-to-Start, Start-to-Start) has been defined multiple times for the same predecessor and successor combination.
- Data Entry Errors: During the creation or modification of project elements, users may inadvertently create duplicate entries.
- System Configuration Issues: In some cases, system settings or configurations may lead to unexpected behavior, causing duplicates to appear.
Solution:
Check Relationships:
- Go to the project structure (WBS elements or activities) where the error is occurring.
- Review the relationships defined for the specific project element.
- Look for any duplicate entries for the same predecessor and successor.
Delete Duplicates:
- If duplicates are found, delete the redundant relationship entries.
- Ensure that only one relationship of each type exists between the same predecessor and successor.
Use Transaction Codes:
- You can use transaction codes like
CJ20N
(Project Builder) orCJ02
(Change Project) to view and edit project relationships.- Navigate to the "Relationships" tab and check for duplicates.
Validation:
- After making changes, validate the project structure to ensure that the error is resolved.
- You can also use the "Check" function in the project builder to identify any remaining issues.
Consult Documentation: If the issue persists, refer to SAP documentation or consult with your SAP support team for further assistance.
Related Information:
By following these steps, you should be able to resolve the PJ680 error and ensure that your project relationships are correctly defined.
Get instant SAP help. Start your 7-day free trial now.
PJ670
Work center & defined twice (Please check)
What causes this issue? The MPX files has the same name several time for the same field <ZH>Short text</>. The project system creates the...
PJ660
Activity element & defined twice (Check your entry)
What causes this issue? The MPX files has the same name several time for the same field <ZH>Activity notes</>. The project system creates...
PJ690
Duration "&" is not in a valid MPX unit (Please correct)
What causes this issue? The unit for time has an invalid MPX format.System Response The system issues an error message and will not allow you to con...
PJ700
PC file not found
What causes this issue? The PC file that you maintained for the upload was not found.System Response INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJE...
Click on this link to search all SAP messages.