Do you have any question about this error?
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 670
Message text: Work center & defined twice (Please check)
The MPX files has the same name several time for the same field
<ZH>Short text</>. The project system creates the number for the work
center from the short text.
INCLUDE 'NA_ALLG_NOVERARBEITUNG' OBJECT DOKU ID TX
Check what you have called the field short text in Microsoft Project(R)
and make any changes necessary.
Please note:
The short text may not be the same for several resources.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
text</>.Error message extract from SAP system. Copyright SAP SE.
PJ670
- Work center & defined twice (Please check) ?The SAP error message PJ670 indicates that a work center has been defined more than once in the system, which can lead to confusion and inconsistencies in project management and resource planning. This error typically occurs in the context of project systems (PS) or production planning (PP) modules when trying to assign a work center to a project or operation.
Cause:
- Duplicate Entries: The most common cause of this error is that the same work center has been entered multiple times in the system, either in the same project or across different projects.
- Configuration Issues: There may be issues in the configuration settings that allow for duplicate entries.
- Data Migration Errors: If data has been migrated from another system, it’s possible that duplicates were created during the migration process.
Solution:
Check Work Center Definitions:
- Go to the transaction code
CR02
(Change Work Center) orCR03
(Display Work Center) and check the work center definitions.- Ensure that the work center in question is not defined more than once.
Review Project Assignments:
- Check the project or network where the error is occurring. Use transaction codes like
CJ20N
(Project Builder) to review the assignments.- Look for any duplicate assignments of the same work center to different activities or operations.
Delete or Modify Duplicates:
- If duplicates are found, you can either delete the unnecessary entries or modify them to ensure that each work center is unique within the context of the project.
Data Consistency Check:
- Run a consistency check on the project or network to identify any other potential issues that may be causing the error.
Consult Documentation:
- Review SAP documentation or help files for any specific guidelines related to work center definitions and project assignments.
Contact SAP Support:
- If the issue persists and you cannot identify the duplicates, consider reaching out to SAP support for further assistance.
Related Information:
CR01
(Create Work Center), CR02
, CR03
, CJ20N
, and CJ02
(Change Project).By following these steps, you should be able to resolve the PJ670 error and ensure that your work center definitions are unique and correctly assigned within your SAP system.
Get instant SAP help. Start your 7-day free trial now.
PJ660
Activity element & defined twice (Check your entry)
What causes this issue? The MPX files has the same name several time for the same field <ZH>Activity notes</>. The project system creates...
PJ650
Activity & defined twice (Please check)
What causes this issue? The MPX files have the same name several times for the same field <ZH>Text10</>. The project system creates the a...
PJ680
Relationship & defined twice (Please check)
What causes this issue? You have entered a relationship with the same type for the same activity several times in field <ZH>predecessor </&g...
PJ690
Duration "&" is not in a valid MPX unit (Please correct)
What causes this issue? The unit for time has an invalid MPX format.System Response The system issues an error message and will not allow you to con...
Click on this link to search all SAP messages.