Message type: E = Error
Message class: PEP - Schedule Manager: Messages
Message number: 232
Message text: The successor node for node with NODE_ID & was not found
One of the tasks refers to a subsequent task that does not
exist. This is not
possible.
Technical information: All tasks with the same task group are connected
to one another in a chain. The content of the
NSIBLING_ID field refers to the
NODE_ID node of the next task in the chain.
If none of the tasks in the task group have this NODE_ID,
the task list is faulty.
Error message extract from SAP system. Copyright SAP SE.
PEP232
- The successor node for node with NODE_ID & was not found ?The SAP error message PEP232, which states "The successor node for node with NODE_ID & was not found," typically occurs in the context of SAP Project Management or SAP Project System (PS) when dealing with project structures, such as Work Breakdown Structures (WBS) or network activities.
Cause:
This error usually arises due to one of the following reasons:
Missing Successor Node: The project structure is incomplete, and the system cannot find the successor node that is supposed to follow the specified node (NODE_ID). This can happen if the project structure was modified, and the successor was deleted or not created properly.
Data Inconsistency: There may be inconsistencies in the project data, such as incorrect links between nodes or missing entries in the database.
Incorrect Configuration: The configuration settings for the project management module may not be set up correctly, leading to issues in how nodes are linked.
Transport Issues: If project structures were transported from one system to another (e.g., from development to production), there may have been issues during the transport process that led to missing nodes.
Solution:
To resolve the PEP232 error, you can take the following steps:
Check Project Structure: Review the project structure in the SAP system to ensure that all nodes are correctly defined and that the successor node exists. You can use transaction codes like
CJ20N
(Project Builder) orCJ03
(Display WBS Element) to inspect the project.Recreate Missing Nodes: If you identify that the successor node is indeed missing, you may need to recreate it or adjust the project structure to ensure that all necessary nodes are present.
Consistency Check: Run consistency checks on the project structure. You can use transaction
CJ_CHECK
to perform a consistency check on the project.Review Transport Logs: If the issue arose after a transport, check the transport logs for any errors or warnings that might indicate what went wrong during the transport process.
Consult Documentation: Review SAP documentation or notes related to project management and the specific error message for any additional guidance or patches that may be available.
Contact SAP Support: If the issue persists and you cannot identify the cause, consider reaching out to SAP support for assistance. They may have additional insights or solutions based on the specific context of your system.
Related Information:
CJ20N
, CJ03
, CJ_CHECK
, and others related to project management.By following these steps, you should be able to diagnose and resolve the PEP232 error in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
PEP231
Nodes with NODE_ID &1 and &2 both occur at end of task group sequence
What causes this issue? One of the task groups has more than one final task. This is not possible. Technical information: All tasks with the same tas...
PEP230
The task group of node NODE_ID = & is not triggered
What causes this issue? The task group that this task belongs to is not triggered in the task list. Technical information: The task group belongs to ...
PEP233
The successor node for node with NODE_ID & is in a different task group
What causes this issue? One of the tasks in the task group refers to a subsequent task that does not appear in the same task group. This is not possi...
PEP234
A loop occurs in the task group for node with NODE_ID &
What causes this issue? One of the tasks in the task group refers to a subsequent task that refers back to the original task, possibly several steps ...