How To Fix PCA039 - The takt unit was changed in &


SAP Error Message - Details

  • Message type: E = Error

  • Message class: PCA - Message Class for Production Campaign

  • Message number: 039

  • Message text: The takt unit was changed in &

  • Show details Hide details
  • What causes this issue?

    You have changed the unit for the takt time. When you create a
    production campaign, the takt time is taken from the material master,
    where the unit for the takt time is always "day".

    System Response

    The functions for calculating the basic start date and finish date as
    well as for creating planned orders use the takt as the duration of an
    order. You can change the takt to create a tighter sequence of planned
    orders and production orders / process orders.
    If you carry out the function for calculating the basic dates, you see
    the basic start time and finish time in the campaign item list, next to
    the start and finish dates. However, these times are only saved in the
    production/process order when you use scheduling types with times.
    Otherwise, when you call up the campaign again, there are no values in
    the basic time fields.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message PCA039 - The takt unit was changed in & ?

    The SAP error message PCA039 indicates that the takt unit has been changed in a production planning context, which can disrupt the production process if not handled correctly. This error typically arises in the context of production planning and control, particularly when dealing with production orders, work centers, or routing.

    Cause:

    The error message PCA039 is triggered when there is a mismatch or inconsistency in the takt time settings. This can occur due to several reasons, including:

    1. Change in Takt Time: The takt time for a work center or production line has been modified, which affects the scheduling and planning of production orders.
    2. Configuration Changes: Changes in the configuration of the production environment, such as updates to work centers, production resources, or routing.
    3. Data Inconsistencies: Inconsistencies in master data related to production planning, such as incorrect settings in the work center or routing.

    Solution:

    To resolve the PCA039 error, you can take the following steps:

    1. Review Changes: Check the recent changes made to the takt time settings in the relevant work center or production line. Ensure that the changes are intentional and correctly configured.

    2. Update Production Orders: If the takt time has changed, you may need to update existing production orders to reflect the new takt time. This can involve re-scheduling or re-planning the orders.

    3. Check Master Data: Verify the master data for the work center, routing, and production resources to ensure that all settings are consistent and correctly defined.

    4. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling takt time changes and related error messages.

    5. Testing: After making the necessary adjustments, test the changes in a development or test environment before applying them to the production environment.

    6. Seek Support: If the issue persists, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.

    Related Information:

    • Takt Time: Takt time is the amount of time available to produce a product in order to meet customer demand. It is a critical metric in lean manufacturing and production planning.
    • Production Planning (PP): SAP's Production Planning module is used for planning and controlling the manufacturing process, including scheduling, capacity planning, and production order management.
    • Error Handling: Familiarize yourself with SAP error handling procedures, as understanding how to interpret and resolve error messages is crucial for effective system management.

    By following these steps and understanding the context of the error, you should be able to address the PCA039 error effectively.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
The AI Support Assistant is great. It provides comprehensive assistance even on the most difficult issues. I highly recommend this service.
Rate 1
John Jordan
SAP Consultant & Author