Message type: E = Error
Message class: OIJ_IF - OIL TSW: Messages for TSW Interfaces Layer
Message number: 180
Message text: Planned End Date/Time to for event &1 not within allowed range
The planned date and time for event &V1& are not within the allowed
range that is determined from reference document &V2&. In this
document, you define a time that the system adds to the schedule date
of &V3& &V4&.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Change the planned date and time for nomination line item event &V1& or
adapt the TSW details for the reference document for event &V1&.
Error message extract from SAP system. Copyright SAP SE.
OIJ_IF180
- Planned End Date/Time to for event &1 not within allowed range ?The SAP error message OIJ_IF180, which states "Planned End Date/Time for event &1 not within allowed range," typically occurs in the context of the SAP Oil and Gas (OIJ) module. This error indicates that the planned end date and time for a specific event (denoted by &1) is outside the permissible range defined in the system.
Cause: Date/Time Configuration: The planned end date/time may be set to a date that is either too far in the past or future, violating the business rules or configuration settings in the system. Event Overlap: The planned end date/time may overlap with other events or activities that have already been scheduled, leading to conflicts. Incorrect Data Entry: There may be a mistake in the data entry process, such as entering the wrong date or time format. System Settings: The system may have specific settings or parameters that restrict the range of dates/times that can be entered for certain events.
Solution: Check
Get instant SAP help. Sign up for our Free Essentials Plan.
OIJ_IF179
Planned End Date/Time from for event &1 not within allowed range
What causes this issue? The planned date and time for event &V1& are not within the allowed range that is determined from reference document ...
OIJ_IF178
Planned Start Date/Time to for event &1 not within allowed range
What causes this issue? The planned date and time for event &V1& are not within the allowed range that is determined from reference document ...
OIJ_IF181
Pegging check failed for route across nomination pegging
What causes this issue? When pegging nomination items across nominations, such as when connecting transport systems, the system performs several chec...
OIJ_IF182
Select one nomination line item for pipeline batch date redetermination
What causes this issue? Exactly one nomination line item has to be selected for pipeline batch date and time redetermination. Note, that this has to ...
Click on this link to search all SAP messages.