How To Fix MPE_INSTALLATION_MSG064 - Network activity &1 starts before predecessor &2 starts


MPE_INSTALLATION_MSG064 - Overview

  • Message type: E = Error

  • Message class: MPE_INSTALLATION_MSG -

  • Message number: 064

  • Message text: Network activity &1 starts before predecessor &2 starts

  • Show details Hide details
  • What causes this issue?

    Two network activities are connected by a precedence relationship and a
    start-start relationship. However, the predecessor activity starts after
    the successor activity starts.

    System Response

    The system does not automatically reschedule network activities

    How to fix this error?

    Reschedule the network activities (using transaction <AB>CJ20N</>) to
    make the schedule feasible.

    Procedure for System Administrators

    The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MPE_INSTALLATION_MSG064 - Network activity &1 starts before predecessor &2 starts ?
    The SAP error message MPE_INSTALLATION_MSG064 indicates that there is a network activity that is starting before its predecessor activity has been completed. This typically occurs in the context of project management or process scheduling within SAP, where activities are interdependent and must follow a specific sequence.
    
    Cause: The error arises when: A network activity (e.g., a task or process) is scheduled to start before its predecessor activity has finished. There may be a misconfiguration in the scheduling of activities, such as incorrect start and finish dates or dependencies not being properly defined. The project or process plan may have been altered, leading to conflicts in the sequence of activities.
    Solution: To resolve this error, you can take the following steps: Check Activity Dependencies: Review the dependencies between the activities in your project or process. Ensure that the predecessor activity is correctly defined and that the successor activity is set to start only after the predecessor has completed. Adjust Scheduling: Modify the

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant