Message type: E = Error
Message class: MPE_INSTALLATION_MSG -
Message number: 064
Message text: Network activity &1 starts before predecessor &2 starts
Two network activities are connected by a precedence relationship and a
start-start relationship. However, the predecessor activity starts after
the successor activity starts.
The system does not automatically reschedule network activities
Reschedule the network activities (using transaction <AB>CJ20N</>) to
make the schedule feasible.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MPE_INSTALLATION_MSG064
- Network activity &1 starts before predecessor &2 starts ?The SAP error message MPE_INSTALLATION_MSG064 indicates that there is a network activity that is starting before its predecessor activity has been completed. This typically occurs in the context of project management or process scheduling within SAP, where activities are interdependent and must follow a specific sequence.
Cause: The error arises when: A network activity (e.g., a task or process) is scheduled to start before its predecessor activity has finished. There may be a misconfiguration in the scheduling of activities, such as incorrect start and finish dates or dependencies not being properly defined. The project or process plan may have been altered, leading to conflicts in the sequence of activities.
Solution: To resolve this error, you can take the following steps: Check Activity Dependencies: Review the dependencies between the activities in your project or process. Ensure that the predecessor activity is correctly defined and that the successor activity is set to start only after the predecessor has completed. Adjust Scheduling: Modify the
Get instant SAP help. Sign up for our Free Essentials Plan.
MPE_INSTALLATION_MSG063
Network activity &1 ends before predecessor &2 ends
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MPE_INSTALLATION_MSG062
Network activity &1 starts before predecessor &2 is completed
What causes this issue? Two network activities are connected by a precedence relationship and a finish-start relationship. However, the predecessor a...
MPE_INSTALLATION_MSG065
Material & is not an end item
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MPE_INSTALLATION_MSG066
Network has comp. demand for major assembly, but network does not exist.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...