Do you have any question about this error?
Message type: E = Error
Message class: MMRP01 - Rapid Planning Matrix
Message number: 239
Message text: You cannot add components to phantom assemblies
In the planned order &V1&, you tried adding a new component to a phantom
assembly.
The system cannot change the order.
You can only add new components at the highest BOM level. You can only
make changes to the structure of a phantom assembly in the master data.
However, any changes to the master data only has an effect on newly
created or newly exploded planned orders.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MMRP01239
- You cannot add components to phantom assemblies ?The SAP error message MMRP01239, which states "You cannot add components to phantom assemblies," typically occurs when you are trying to add components to a phantom assembly in the SAP system. Phantom assemblies are special types of assemblies that are not stocked as separate items but are used in the bill of materials (BOM) to simplify the structure of complex products.
Cause:
The error arises because:
- Phantom Assembly Definition: Phantom assemblies are defined in the system to act as placeholders in a BOM. They are not treated as independent stock items, and therefore, you cannot add components directly to them.
- BOM Structure: The structure of the BOM for a phantom assembly is designed to automatically include its components in the parent assembly's BOM, rather than allowing for direct component additions.
Solution:
To resolve this error, consider the following steps:
Review BOM Structure: Check the BOM structure for the phantom assembly. Ensure that the components you want to add are already included in the BOM of the phantom assembly. If they are not, you will need to modify the BOM of the phantom assembly itself.
Modify Phantom Assembly: If you need to add components, you should do so in the BOM of the phantom assembly rather than trying to add them directly to the phantom assembly itself.
Use Alternative Assemblies: If the components need to be treated as separate stock items, consider using a regular assembly instead of a phantom assembly.
Consult Documentation: Refer to SAP documentation or your organization's SAP guidelines for managing BOMs and phantom assemblies to ensure compliance with best practices.
Check User Permissions: Ensure that you have the necessary permissions to modify BOMs and assemblies in the SAP system.
Related Information:
By following these steps, you should be able to address the MMRP01239 error effectively.
Get instant SAP help. Start your 7-day free trial now.
MMRP01238
Component variant of a phantom assembly must be unique
What causes this issue? You tried to add a component with a component variant at node &V2& of order &V1& for which a phantom assembly...
MMRP01237
Phantom assembly without material: Node &2 of order &1 will not be firmed
What causes this issue? A phantom assembly exists at node &V2& of the planned order &V1& for which you have not entered a material nu...
MMRP01240
ATP relevant components exist in the phantom assembly without material
What causes this issue? A component to be checked is in a phantom assembly for which you did not enter any material number in the access variant or i...
MMRP01241
RPM Order: Changing components in phantom assemblies not allowed
What causes this issue? You tried to change the component of a phantom assembly in a planned order which is planned with the matrix.System Response ...
Click on this link to search all SAP messages.