Do you have any question about this error?
Message type: E = Error
Message class: MMRP01 - Rapid Planning Matrix
Message number: 210
Message text: 'Explode Det.Scheduling Matrix Only' is not possible for product &1 in &2
You have selected the function to <DS:DE.MMRP_FP_EXPLOSION>
explode orders from the detailed scheduling matrix only</> for product
&V1& in location &V2&. In the additional data for RPM materials, the
settings you have made for this product mean that the
<DS:DE.MMRP_KEEP_FC_BITS>crosses are kept</> in the planning matrices
as well.
You cannot use this function here, because the system must ensure that
there are no differences between the planning horizon and the horizon
for detailed scheduling in the master data stored in the planning
matrices.
Select the function to <DS:DE.MMRP_DO_EXPLOSION>explode all the
matrices,</> or change the settings in the <DS:TRAN.MDRPM>Additional
Data for RPM Materials
</>.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MMRP01210
- 'Explode Det.Scheduling Matrix Only' is not possible for product &1 in &2 ?The SAP error message MMRP01210, which states "'Explode Det. Scheduling Matrix Only' is not possible for product &1 in &2," typically occurs in the context of production planning and scheduling within SAP. This error indicates that the system is unable to explode the detailed scheduling matrix for a specific product in a given plant or location.
Cause:
The error can be caused by several factors, including:
Product Configuration Issues: The product may not be properly configured for detailed scheduling. This could include missing or incorrect master data settings.
Scheduling Matrix Not Defined: The scheduling matrix for the product may not be defined or may not be set up correctly in the system.
Product Status: The product might be in a status that does not allow for scheduling or production (e.g., inactive, blocked).
Plant-Specific Settings: There may be plant-specific settings that prevent the scheduling matrix from being used for the product in the specified plant.
Dependencies or Constraints: There may be dependencies or constraints in the production process that prevent the scheduling matrix from being applied.
Solution:
To resolve the MMRP01210 error, you can take the following steps:
Check Product Master Data:
- Ensure that the product master data is complete and correctly configured. This includes checking the material type, production type, and any relevant settings in the material master.
Review Scheduling Matrix:
- Verify that the scheduling matrix is defined for the product in question. You can do this by navigating to the relevant configuration settings in SAP.
Check Product Status:
- Ensure that the product is active and not blocked for production or scheduling. You can check the status in the material master.
Plant-Specific Configuration:
- Review the plant-specific settings to ensure that they allow for the use of the scheduling matrix for the product.
Consult Documentation:
- Refer to SAP documentation or help resources for detailed information on how to set up and troubleshoot scheduling matrices.
Contact SAP Support:
- If the issue persists after checking the above points, consider reaching out to SAP support for further assistance.
Related Information:
By following these steps, you should be able to identify the root cause of the MMRP01210 error and implement the necessary solutions to resolve it.
Get instant SAP help. Start your 7-day free trial now.
MMRP01209
The product master for colored material &1 has not been created
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MMRP01208
An internal error has occurred: unknown matrix
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MMRP01211
You have not assigned a production calendar to location &1
What causes this issue? In order to carry out fixing you must assign a <DS:DE./SAPAPO/PPCAL>production calendar</> to location &V1&am...
MMRP01212
Error scheduling horizon for detailed scheduling using production calend.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.