Do you have any question about this error?
Message type: E = Error
Message class: MMPUR_SPROC - Message class for service procurement
Message number: 041
Message text: The validity period of the contract &1 ends too early
The validity period of contract &V1& ends at &V2&.
The period of performance of the current item starts at &V3&.
Both periods need to overlap.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MMPUR_SPROC041
- The validity period of the contract &1 ends too early ?The SAP error message MMPUR_SPROC041 indicates that there is an issue with the validity period of a contract in the procurement process. Specifically, it means that the end date of the contract is set too early, which prevents the system from processing the related procurement activities.
Cause:
- Contract Validity Dates: The contract has an end date that is earlier than the date of the procurement transaction (e.g., purchase order or requisition).
- Incorrect Data Entry: The validity period may have been incorrectly entered during contract creation or modification.
- Contract Type Restrictions: Certain contract types may have specific validity requirements that are not being met.
Solution:
- Check Contract Dates: Review the validity dates of the contract in question. Ensure that the end date is set to a date that is later than the date of the procurement transaction.
- Modify Contract: If the end date is indeed too early, you will need to modify the contract to extend the validity period. This can be done through the contract management transaction in SAP (e.g., ME31K for creating contracts, ME32K for changing contracts).
- Review Related Documents: Ensure that any related documents (like purchase orders) are also aligned with the contract's validity period.
- Consult Documentation: If you are unsure about the correct validity period, consult your organization's procurement policies or SAP documentation for guidance on contract management.
Related Information:
By addressing the validity period of the contract and ensuring it aligns with your procurement activities, you should be able to resolve the error message MMPUR_SPROC041.
Get instant SAP help. Start your 7-day free trial now.
MMPUR_SPROC040
The validity period of the contract &1 starts too late
What causes this issue? The validity period of contract &V1& starts at &V2&. The period of performance of the current item ends at &a...
MMPUR_SPROC039
Only contracts with the same supplier and purchasing organization allowed
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MMPUR_SPROC042
Contract &1 does not have any fitting items
What causes this issue? A contract can only be used here if it has at least one item fulfilling the following conditions: The contract item is of pro...
MMPUR_SPROC043
Select 'Goods Receipt' for items with product type group 'Service'.
What causes this issue? For purchase order items with product type group 'Service' and consumption posting 'Unknown', the flag ...