Do you have any question about this error?
Message type: E = Error
Message class: MFLOW - Messages for Message Destination PI_MFLOW (PP-PI)
Message number: 018
Message text: Bulk material &1 not defined as header material of order &2.
Bulk material &1 is not the header material of order &2 issueing the
material.
However, the quantity to be entered for confirmations at header level
always refers to the order's header material. For this reason, you
cannot confirm the quantity of the bulk material for the order
producing the material.
When processing message PI_MFLOW, the system skips the confirmation at
header level for the order producing the material.
You must confirm the producing order in a different way.
Error message extract from SAP system. Copyright SAP SE.
MFLOW018
- Bulk material &1 not defined as header material of order &2. ?The SAP error message MFLOW018 indicates that a bulk material (in this case, represented by
&1
) is not defined as a header material for the specified order (&2
). This error typically occurs in the context of production orders or process orders where bulk materials are involved.Cause:
- Material Configuration: The bulk material you are trying to use is not set up correctly in the system. It may not be assigned as a header material in the order you are working with.
- Order Type: The order type you are using may not support the bulk material as a header material.
- Missing Master Data: The necessary master data for the bulk material or the order may be incomplete or incorrectly configured.
- Incorrect Order Reference: The order you are referencing may not be the correct one for the bulk material you are trying to use.
Solution:
- Check Material Master: Verify that the bulk material is correctly defined in the material master. Ensure that it is set up as a valid material type and that all necessary views (like Basic Data, Purchasing, and MRP) are properly maintained.
- Check Order Configuration: Ensure that the order type you are using allows for the bulk material as a header material. You may need to consult with your SAP configuration team to confirm this.
- Define Header Material: If the bulk material is not defined as a header material for the order, you will need to add it. This can typically be done in the order creation or change transaction (e.g., CO01, CO02).
- Review Order Details: Double-check the order details to ensure that you are referencing the correct order and that all required fields are filled out correctly.
- Consult Documentation: If you are unsure about the configuration or setup, refer to SAP documentation or consult with your SAP support team for guidance.
Related Information:
If the issue persists after following these steps, it may be beneficial to engage with your SAP support team or a consultant who specializes in SAP logistics and production processes.
Get instant SAP help. Start your 7-day free trial now.
MFLOW017
Message destination can only process one message. & have been sent.
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MFLOW016
Inspection point processing defined for order &. Function is canceled!
What causes this issue? You attempted to post a material flow between two orders. However, inspection point processing has been defined in the source...
MFLOW019
Error when reading the unit of measure & (from table T006)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MFLOW020
The produced quantity &1 &2 for order &3 was rounded up.
What causes this issue? As specified in the Customizing settings for the unit of measurement, the system rounds up the produced quantity &1 &...