How To Fix MD504 - &1: Preference for operation at component level (U1)


MD504 - Overview

  • Message type: E = Error

  • Message class: MD - Material Requirements Planning (MRP)

  • Message number: 504

  • Message text: &1: Preference for operation at component level (U1)

  • Show details Hide details
  • What causes this issue?

    The rescheduling check has calculated that the receipts of the
    components are not available until too late of a date. The delay time
    displayed indicates the number of workdays by which the component
    receipt with the greatest delay for meeting the necessary availability
    date is delayed in realation to the whole BOM structure. The delay
    times for individual component receipts are added by the BOM hierarchy
    levels.

    System Response

    This exception message appears in the MRP list for a planning run in
    the main memory.

    How to fix this error?

    Check whether you can give preference to the receipts for the
    components causing the delay. You can access these receipts by choosing
    the function 'Order structure' for the receipt you are viewing.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MD504 - &1: Preference for operation at component level (U1) ?
    The SAP error message MD504 indicates that there is a preference for an operation at the component level, which typically arises in the context of production planning and scheduling. This error can occur when there is a conflict in the planning data, particularly when the system is trying to allocate resources or schedule operations based on the preferences set for components in a bill of materials (BOM) or routing.
    
    Cause: Component Preferences: The error often arises when there are conflicting preferences for operations at the component level. For example, if a component has a specific operation assigned to it, but the system is trying to allocate a different operation based on the overall production order or planning strategy. Routing Issues: There may be issues with the routing data, such as missing or incorrect operation sequences that lead to conflicts in scheduling. Master Data Inconsistencies: Inconsistencies in master data, such as BOMs, routings, or work

    Already have an account? Login here!




Instant HelpGet instant SAP help. Sign up for our Free Essentials Plan.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant