Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 504
Message text: &1: Preference for operation at component level (U1)
The rescheduling check has calculated that the receipts of the
components are not available until too late of a date. The delay time
displayed indicates the number of workdays by which the component
receipt with the greatest delay for meeting the necessary availability
date is delayed in realation to the whole BOM structure. The delay
times for individual component receipts are added by the BOM hierarchy
levels.
This exception message appears in the MRP list for a planning run in
the main memory.
Check whether you can give preference to the receipts for the
components causing the delay. You can access these receipts by choosing
the function 'Order structure' for the receipt you are viewing.
Error message extract from SAP system. Copyright SAP SE.
MD504
- &1: Preference for operation at component level (U1) ?The SAP error message MD504 indicates that there is a preference for an operation at the component level, which typically arises in the context of production planning and scheduling. This error can occur when there is a conflict in the planning data, particularly when the system is trying to allocate resources or schedule operations based on the preferences set for components in a bill of materials (BOM) or routing.
Cause:
- Component Preferences: The error often arises when there are conflicting preferences for operations at the component level. For example, if a component has a specific operation assigned to it, but the system is trying to allocate a different operation based on the overall production order or planning strategy.
- Routing Issues: There may be issues with the routing data, such as missing or incorrect operation sequences that lead to conflicts in scheduling.
- Master Data Inconsistencies: Inconsistencies in master data, such as BOMs, routings, or work centers, can also lead to this error.
- Capacity Constraints: If there are capacity constraints that prevent the system from scheduling the preferred operation, this error may occur.
Solution:
- Check Routing and BOM: Review the routing and BOM for the affected material. Ensure that the operations and components are correctly defined and that there are no conflicts.
- Adjust Preferences: If there are specific preferences set for operations at the component level, consider adjusting them to resolve the conflict. This may involve changing the operation assignment or modifying the preference settings.
- Review Capacity Planning: Check the capacity planning settings and ensure that there are sufficient resources available to meet the production requirements. If necessary, adjust the capacity or scheduling parameters.
- Run MRP Again: After making the necessary adjustments, run the Material Requirements Planning (MRP) process again to see if the error persists.
- Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling this error in your version of SAP.
Related Information:
MD04
(Stock/Requirements List) or CO02
(Change Production Order) to analyze the situation further.If the issue persists after following these steps, it may be beneficial to involve your SAP support team or a consultant with expertise in production planning and scheduling.
Get instant SAP help. Start your 7-day free trial now.
MD503
&1: Finish date of components in past (T4)
What causes this issue? The finish date of the order proposals for the components is in the past.System Response This exception message appears in t...
MD502
&1: Start date of components in past (T3)
What causes this issue? The start date of order proposals for the components is in the past.System Response This exception message appears in the MR...
MD505
&1: Move operation to component level (U2)
What causes this issue? The rescheduling check has determined that the receipts for the components should be changed to avoid excessive warehouse sto...
MD510
Overflow: More than 9999 items in BOM recursive for BOM &?
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...