  • What causes this issue?

    The rescheduling check has calculated that the receipts of the
    components are not available until too late of a date. The delay time
    displayed indicates the number of workdays by which the component
    receipt with the greatest delay for meeting the necessary availability
    date is delayed in realation to the whole BOM structure. The delay
    times for individual component receipts are added by the BOM hierarchy
    levels.

    System Response

    This exception message appears in the MRP list for a planning run in
    the main memory.

    How to fix this error?

    Check whether you can give preference to the receipts for the
    components causing the delay. You can access these receipts by choosing
    the function 'Order structure' for the receipt you are viewing.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message MD504 - &1: Preference for operation at component level (U1) ?

    The SAP error message MD504 indicates that there is a preference for an operation at the component level, which typically arises in the context of production planning and scheduling. This error can occur when there is a conflict in the planning data, particularly when the system is trying to allocate resources or schedule operations based on the preferences set for components in a bill of materials (BOM) or routing.

    Cause:

    1. Component Preferences: The error often arises when there are conflicting preferences for operations at the component level. For example, if a component has a specific operation assigned to it, but the system is trying to allocate a different operation based on the overall production order or planning strategy.
    2. Routing Issues: There may be issues with the routing data, such as missing or incorrect operation sequences that lead to conflicts in scheduling.
    3. Master Data Inconsistencies: Inconsistencies in master data, such as BOMs, routings, or work centers, can also lead to this error.
    4. Capacity Constraints: If there are capacity constraints that prevent the system from scheduling the preferred operation, this error may occur.

    Solution:

    1. Check Routing and BOM: Review the routing and BOM for the affected material. Ensure that the operations and components are correctly defined and that there are no conflicts.
    2. Adjust Preferences: If there are specific preferences set for operations at the component level, consider adjusting them to resolve the conflict. This may involve changing the operation assignment or modifying the preference settings.
    3. Review Capacity Planning: Check the capacity planning settings and ensure that there are sufficient resources available to meet the production requirements. If necessary, adjust the capacity or scheduling parameters.
    4. Run MRP Again: After making the necessary adjustments, run the Material Requirements Planning (MRP) process again to see if the error persists.
    5. Consult Documentation: Refer to SAP documentation or help resources for specific guidance on handling this error in your version of SAP.

    Related Information:

    • Transaction Codes: You may need to use transaction codes like MD04 (Stock/Requirements List) or CO02 (Change Production Order) to analyze the situation further.
    • SAP Notes: Check for any relevant SAP Notes that may address this specific error or provide additional troubleshooting steps.
    • User Forums: Consider visiting SAP community forums or user groups where similar issues may have been discussed, and solutions shared.

    If the issue persists after following these steps, it may be beneficial to involve your SAP support team or a consultant with expertise in production planning and scheduling.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating
ERPlingo simplifies finding the accurate answers to SAP message errors. I now use every week. A must have tool for anyone working with SAP! Highly recommended!
Rate 1
Kent Bettisworth
Executive SAP Consultant