Do you have any question about this error?
Message type: E = Error
Message class: MD - Material Requirements Planning (MRP)
Message number: 190
Message text: Different periods not possible during activation
During activiation of the planned independent requirement version,
several versions with varying activation periods were selected.
The system does not support activation of several planned independent
requirement versions with varing activation periods.
Tailor the activation periods to the individual planned independent
requirement versions or activate each planned independent requirement
version separately.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
MD190
- Different periods not possible during activation ?The SAP error message MD190 ("Different periods not possible during activation") typically occurs in the context of Material Requirements Planning (MRP) when there is an inconsistency in the planning data for a material. This error usually arises during the activation of planning data for a material in the MRP area, particularly when the system detects that the periods being referenced for planning do not align correctly.
Causes:
- Inconsistent Planning Data: The planning data for the material may have been changed or not properly maintained, leading to discrepancies in the periods defined for planning.
- Different Period Settings: The periods defined in the MRP settings (like planning horizon, planning periods, etc.) may not match the periods defined in the material master or other related settings.
- Changes in MRP Parameters: If MRP parameters have been changed after the initial planning run, it can lead to inconsistencies.
- Master Data Issues: Issues with the material master data, such as incorrect or missing information in the MRP views.
Solutions:
- Check MRP Settings: Review the MRP settings for the material and ensure that the periods defined are consistent across all relevant settings.
- Recheck Material Master Data: Go to the material master (transaction MM03) and check the MRP views to ensure that all necessary data is correctly maintained.
- Re-run MRP: If changes have been made to the MRP parameters or material master, consider re-running the MRP for the affected materials to regenerate the planning data.
- Consistency Check: Use transaction MD02 or MD03 to check the planning data for the material and ensure that there are no inconsistencies.
- Review Planning File Entries: Check the planning file entries (transaction MD21) to see if there are any entries that might be causing the issue.
- Consult SAP Notes: Look for any relevant SAP Notes that might address this specific error or provide additional troubleshooting steps.
Related Information:
If the issue persists after trying the above solutions, it may be beneficial to consult with your SAP support team or reach out to SAP support for further assistance.
Get instant SAP help. Start your 7-day free trial now.
MD183
Lot size procedure &1 is not defined
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MD182
Lot size procedure &1 being used is not gross lot size procedure
What causes this issue? The lot-sizing procedure entered does not correspond to the requirements of a long-term lot size. Only lot-for-lot order quan...
MD200
*****COMMENT: Messages for CO integration (Maintain T442C)
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
MD201
Version &1 is not a planned version
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
Click on this link to search all SAP messages.