Message type: E = Error
Message class: M3 - Material Master
Message number: 284
Message text: Planned delivery time is 0 for ext. procured material
You are creating a master record for a material that is to be procured
externally. However, you have not entered a planned delivery time.
A planned delivery time of zero only makes sense if the material can be
procured in less than a day. This is possibly the case, for example,
when stock is transferred from one plant to another.
INCLUDE NA_SACHVERHALT
Error message extract from SAP system. Copyright SAP SE.
M3284
- Planned delivery time is 0 for ext. procured material ?The SAP error message M3284, which states "Planned delivery time is 0 for ext. procured material," typically occurs when you are trying to create a purchase order or a production order for a material that is externally procured, but the system has not been configured with a planned delivery time for that material. This planned delivery time is essential for the system to calculate the expected delivery dates and manage inventory effectively.
Cause: Missing Planned Delivery Time: The material master record for the externally procured material does not have a planned delivery time set. Incorrect Material Type: The material may not be set up correctly as an externally procured material.
Configuration Issues: There may be issues in the configuration of the purchasing or material management settings in SAP.
Solution: To resolve this error, you can take the following steps: Check Material Master Record: Go to the material master record (transaction code MM02). Check the purchasing view of the material. Ensure
Get instant SAP help. Sign up for our Free Essentials Plan.
M3283
MRP controller & not defined as buyer
Self-Explanatory Message Since SAP believes that this specific error message is 'self-explanatory,' no more information has been given.The majority of...
M3282
MRP controller & is not defined in plant &
INCLUDE NA_WERTEKOMBError message extract from SAP system. Copyright SAP SE. ...
M3285
In-house production time is 0 for material produced in-house
What causes this issue? You are creating a master record for a material that is to be produced in-house. However, you have not entered an in-house pr...
M3286
Reorder level lower than safety stock
What causes this issue? You have specified a reorder point that is lower than the safety stock. Since the reorder point includes the safety stock, it...