Message type: E = Error
Message class: KQ - Error Messages for Customizing Product Costing
Message number: 143
Message text: Status no. of status TECO must be higher than that of status REL
The valuation method for <DS:GLOS.results_analysis>results analysis</>
or for the calculation of <DS:GLOS.work_in_process>work in process</>
(WIP) is selected through the status of the order or project. If more
than one status is set for the order or project when you perform
results analysis or <DS:GLOS.WIP_calculation>WIP calculation</>, the
system uses the status numbers to select the valuation method.
In your case, the status number you entered for the status
<ZH>Technically completed</> is lower than or the same as the status
number for the status <ZH>Released</>. However, the user sets the
status Technically completed <ZH>after</> the status Released.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Check the status number of the status <ZH>Released</> and change the
status number of the status <ZH>Technically completed</>.
Error message extract from SAP system. Copyright SAP SE.
KQ143
- Status no. of status TECO must be higher than that of status REL ?The SAP error message KQ143, which states "Status no. of status TECO must be higher than that of status REL," typically occurs in the context of controlling (CO) and project systems (PS) when trying to change the status of a project or order. This error indicates that the system is enforcing a status sequence that must be followed when managing project or order statuses.
Cause:
The error arises because the system has a predefined sequence of statuses for project management or order management. In this case, the status "TECO" (Technically Completed) must be set after the status "REL" (Released). If you attempt to set the status TECO without first ensuring that the status REL is properly set and in the correct sequence, the system will throw this error.
Solution:
To resolve this error, you should follow these steps:
Check Current Status: Verify the current status of the project or order. You can do this by navigating to the relevant transaction (e.g., CJ20N for project management or CO02 for order management) and checking the status overview.
Change Status Sequence:
- If the project or order is not yet released (REL), you need to release it first. This can typically be done by selecting the project/order and choosing the option to release it.
- After the project/order is released, you can then proceed to set the status to TECO.
Use the Correct Transactions: Ensure you are using the correct transactions for changing statuses. For example, use CJ20N for projects or CO02 for production orders.
Authorization: Ensure that you have the necessary authorizations to change the status of the project or order. Lack of proper authorization can sometimes lead to unexpected errors.
Consult Documentation: If you are unsure about the status sequence or the implications of changing statuses, consult your organization's SAP documentation or reach out to your SAP support team for guidance.
Related Information:
By following these steps, you should be able to resolve the KQ143 error and successfully manage the statuses of your projects or orders in SAP.
Get instant SAP help. Start your 7-day free trial now.
KQ142
Status no. of status FNBL must be lower than that of status TECO
What causes this issue? The valuation method for <DS:GLOS.results_analysis>results analysis</> or for the calculation of <DS:GLOS.work...
KQ141
Status no. of status FNBL must be higher than that of status REL
What causes this issue? The valuation method for <DS:GLOS.results_analysis>results analysis</> or for the calculation of <DS:GLOS.work...
KQ144
Status no. of status TECO must be higher than that of status DLV
What causes this issue? The valuation method for <DS:GLOS.results_analysis>results analysis</> or for the calculation of <DS:GLOS.work...
KQ145
Status no. of status TECO must be higher than that of status FNBL
What causes this issue? The valuation method for <DS:GLOS.results_analysis>results analysis</> and for the calculation of <DS:GLOS.wor...