Message type: E = Error
Message class: KPN - Costing: Networks, Projects
Message number: 052
Message text: Material &1 for WBS element &2 has already been valuated
Material &V1& has already been valued due to goods being received into
stock in WBS element &V2&.
The price determined when the goods were received is used in the
network costing. Any unit costing maintained for the material component
is ignored.
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
KPN052
- Material &1 for WBS element &2 has already been valuated ?The SAP error message KPN052 indicates that a material has already been valuated for a specific Work Breakdown Structure (WBS) element. This typically occurs in the context of project accounting or controlling when you attempt to perform a valuation or posting that conflicts with existing valuations for that WBS element.
Cause:
- Duplicate Valuation: The material has already been assigned a valuation for the specified WBS element, and the system does not allow for multiple valuations.
- Incorrect Posting: You may be trying to post a transaction that is not allowed because the material is already linked to a valuation.
- Configuration Issues: There may be configuration settings in the system that prevent multiple valuations for the same material and WBS element.
Solution:
- Check Existing Valuations: Review the existing valuations for the material and WBS element combination. You can do this by navigating to the relevant transaction codes (e.g., CJI3 for project reports) to see the current status.
- Adjust the Posting: If you are trying to post a new valuation, consider whether it is necessary. If the valuation is already correct, you may not need to post again.
- Use Different WBS Element: If you need to perform a new valuation, consider using a different WBS element that does not have an existing valuation for that material.
- Consult Documentation: Review SAP documentation or consult with your SAP support team to understand the specific configuration settings that may be affecting this behavior.
- Error Handling: If you believe this error is incorrect, you may need to check for any inconsistencies in the data or consult with your technical team to investigate further.
Related Information:
By following these steps, you should be able to resolve the KPN052 error and understand the underlying issues related to material valuation in your SAP system.
Get instant SAP help. Start your 7-day free trial now.
KPN051
Adapt invoicing plan for material component
What causes this issue? You have used a unit costing to recalculate the price of the material component. An invoicing plan with partial invoicing by ...
KPN050
Milestone dates are not copied to invoicing plan for comp. &1, acty &2
What causes this issue? The items in the invoiding plan are connected to milestones. The changed milestone dates cannot be adjusted in the invoicing ...
KPN053
Valuation for material &1 has already been made in the operative project
What causes this issue? Material &V1& for WBS element &V2& has been valued in the operative project due to a goods receipt. If you tr...
KPN054
A costing for material &2 has already been maintained re WBS el. &1
What causes this issue? The materials in valuated project stock are valued at the level of the WBS element, material, and plant. A price has already ...
Click on this link to search all SAP messages.