How To Fix KP292 - &1: Not all costs could be assigned to the cost component structure


SAP Error Message - Details

  • Message type: E = Error

  • Message class: KP - CO-OM Planning

  • Message number: 292

  • Message text: &1: Not all costs could be assigned to the cost component structure

  • Show details Hide details
  • What causes this issue?

    Object &V1& contains costs that cannot be assigned to the cost
    component structure for the cost component split of the primary costs.

    System Response

    This can happen if cost elements have not been assigned to a cost
    component, or if a cost component only takes into account variable
    costs, even though there are fixed costs present.

    How to fix this error?

    Define a remaining cost component with an empty cost element range,
    which can take these costs. If you do not require a complete assignment
    of the costs for the cost component structure, then you can change this
    message into a note, or switch it off. See the implementation guide
    (IMG) for General Controlling under the
    <DS:SIMG.SIMG_CFMENUORK3OBA5>"Change Message Control"</> activity (work
    area "KP", message number "292"). If you do not enter a user name, this
    change applies to all users.

    Error message extract from SAP system. Copyright SAP SE.


Smart SAP Assistant

  • What is the cause and solution for SAP error message KP292 - &1: Not all costs could be assigned to the cost component structure ?

    The SAP error message KP292 indicates that not all costs could be assigned to the cost component structure during the process of cost planning or cost allocation. This error typically arises in the context of controlling (CO) and can occur for various reasons. Here’s a breakdown of the potential causes, solutions, and related information:

    Causes of Error KP292

    1. Missing Cost Component Structure: The cost component structure may not be defined or may not include all the necessary cost components for the costs being processed.

    2. Inconsistent Cost Elements: The cost elements used in the transaction may not be assigned to the appropriate cost components in the cost component structure.

    3. Incorrect Configuration: There may be configuration issues in the controlling area or the cost component structure itself.

    4. Data Issues: There may be issues with the data being processed, such as missing or incorrect entries in the cost planning or allocation documents.

    5. Cost Component Structure Not Active: The cost component structure may not be active for the period in which the costs are being assigned.

    Solutions to Error KP292

    1. Check Cost Component Structure:

      • Go to the configuration settings for the cost component structure (Transaction code: OKTZ).
      • Ensure that the cost component structure is correctly defined and includes all necessary cost components.
    2. Verify Cost Elements:

      • Check the cost elements involved in the transaction (Transaction code: KA03).
      • Ensure that they are assigned to the correct cost components in the cost component structure.
    3. Review Configuration:

      • Review the configuration settings in the controlling area to ensure that they are set up correctly.
      • Check if the cost component structure is assigned to the relevant controlling area.
    4. Data Validation:

      • Validate the data being processed to ensure that all necessary entries are complete and correct.
      • Look for any missing or incorrect entries in the cost planning or allocation documents.
    5. Activate Cost Component Structure:

      • If the cost component structure is not active for the relevant period, activate it in the configuration settings.
    6. Consult Documentation:

      • Refer to SAP documentation or help resources for additional guidance on the specific configuration and setup for cost component structures.

    Related Information

    • Transaction Codes:

      • OKTZ: Cost Component Structure Configuration
      • KA03: Display Cost Element
      • KP06: Change Plan Data
      • KP26: Change Plan Data for Cost Centers
    • SAP Notes: Check for any relevant SAP Notes that may address specific issues related to error KP292. You can search for notes in the SAP Support Portal.

    • Testing: After making changes, perform a test run to ensure that the error is resolved and that costs are being assigned correctly to the cost component structure.

    By following these steps, you should be able to identify the cause of the KP292 error and implement the necessary solutions to resolve it. If the issue persists, consider reaching out to your SAP support team or consulting with an SAP expert for further assistance.

    • Do you have any question about this error?


      Upgrade now to chat with this error.


Instant HelpGet instant SAP help. Start your 7-day free trial now.


Related SAP Error Messages

Click the links below to see the following related messages:

Click on this link to search all SAP messages.


Rating